HomeMy WebLinkAbout02_113 CC ResolutionRESOLUTION NO 02113
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
TEMECULA APPROVING PLANNING APPLICATION NO 01
0230 TENTATIVE TRACT MAP NO 29353 A SUBDIVISION
OF 8047 ACRES INTO 39 LOTS AND 8 STREET LOTS WITHIN
THE RORIPAUGH RANCH SPECIFIC PLAN LOCATED NEAR
THE FUTURE INTERSECTION OF BUTrERFIELD STAGE
ROAD AND NICOLAS ROAD AND FURTHER IDENTIFIED AS
ASSESSOR PARCEL NOS 957130001 and 002 957340001
003 007 008 AND 958260001 AND 002
WHEREAS Ashby USA LLC filed Planning Application No PA010230 AND PA01
0253 the Application in a manner in accord with the City of Temecula General Plan
Development Code and Subdivision Ordinance
WHEREAS the Application was processed including but not limited to public notice n
the time and manner prescribed by State and local law
WHEREAS the Planning Commission at a regular meeting considered the Application
on October 16 2002 at a duly noticed public hearing as prescribed by law at which time the
City staff and interested persons had an opportunity to and did testify either in support or
opposition to this matter
WHEREAS at the conclusion of the Commission hearings and after due consideration
of the testimony the Commission recommended approval of the Application subject to and
based upon the findings set forth hereunder
WHEREAS the City Council considered the Application on November 26 2002 at a
duly noticed public hearing as prescribed by law at which time the City staff and interested
persons had an opportunity to and did testify either in support or opposition to this matter
WHEREAS at the conclusion of the Council hearing and after due consideration of the
testimony the Council approved of the Application and certified the Environmental Impact
Report and adopted the Mitigation Monitoring Program after finding that the project proposed in
the Application conformed to the City of Temecula General Plan
WHEREAS all legal preconditions to the adoption of this Resolution have occurred
NOW THEREFORE THE CITY COUNCIL OF THE CITY OF TEMECULA DOES
RESOLVE DETERMINE AND ORDER AS FOLLOWS
Section 1 That the above recitations are true and correct and are hereby
incorporated by reference
Section 2 Findinqs That the City Council in approving the Application hereby
makes the following findings as required in Section 1609140of the Temecula Municipal Code
A The proposed subdivision and the design and improvements of the subdivision is
consistent with the Development Code General Plan any applicable specific plan and the City
of Temecula Municipal Code
RResos 2002Resos 02113 1
B The proposed subdivision map is consistent with the subject specific plan and
related General Plan Amendment
C The tentative map does not propose to divide land which is subject to a contract
entered into pursuant to the California Land Conservation Act of 1965 or the land is subject to a
Land Conservation Act contract but the resulting parcels following division of the land will not be
too small to sustain their agricultural use
D The site is physically suitable for the type and proposed density of development
proposed by the tentative map
E The design of the subdivisions and the proposed improvements with conditions
of approval are not likely to cause significant environmental damage or substantially and
avoidably injure fish or wildlife or their habitat as no sensitive species or habitant exist within the
project boundaries
F An environmental impact report has been prepared and a finding has been
made pursuant to Public Resources Code Section 21081 a 3 finding that specific economic
social or other considerations make infeasible mitigation measures or project alternatives
identified in the environmental impact report
G The design of the subdivisions and the type of improvements are not likely to
cause serious public health problems
H The design of the subdivisions provides for future passive or natural heating or
cooling opportunities in the subdivision to the extent feasible
I The design of the subdivisions and the type of improvements will not conflict with
easements acquired by the public at large for access through or use of property within the
proposed subdivision or the design of the alternate easements which are substantially
equivalent to those previously acquired by the public will be provided
Quimby
The subdivisions are consistent with the Citys parkland dedication requirements
Section 3 Environmental Compliance Residential projects approved under a
Specific Plan are exempt from further environmental review pursuant to Section 15182 of the
California Environmental Quality Act Guidelines All environmental impacts were previously
identified and in the Final Environmental Impact Report FEIR and Mitigation Monitoring
Program in order to approve the project
Section 4 Conditions The City Council of the City of Temecula approves Planning
Application No 010230 Tentative Tract Map No 29353 Exhibit A for the subdivision Of
8047acres into 39 lots and 8 street lots within the Roripaugh Ranch Specific Plan subject to
the project specific conditions set forth on Exhibit B attached hereto and incorporated herein by
this reference together with any and all other necessary conditions that may be deemed
necessary for the property located near the future intersection of Buttedield Stage Road and
Nicolas Road and further identified as Assessor Parcel Nos 957130001 and 002 957340
001003 007 008 and 958260001 and 002
RResos 2002Resos 02113 2
Section 5 PASSED APPROVED AND ADOPTED this 26th day of November 2002
Ron Roberts Mayor
STATE OF CALIFORNIA
COUNTY OF RIVERSIDE ss
CITY OF TEMECULA
I Susan W Jones CMC City Clerk of the City of Temecula do hereby certify that
Resolution No 02113 was duly and regularly adopted by the City Council of the City of
Temecula at a regular meeting thereof held on the 26th of November 2002 by the following
vote
AYES COUNCILMEMBERS Comerchero Naggar Pratt Stone Roberts
NOES COUNCILMEMBERS None
ABSENT COUNCILMEMBERS None
ABSTAIN COUNCILMEMBERS None
City Clerk
RResos 2002Resos 02113 3
EXHIBIT A
FOR ATrACHMENT NO 5
TENTATIVE TRACT MAP NO 29353
RResos 2002Resos 02113 4
REVISED CONDITIONS OF APPROVAL
MAY 17 2006 PLANNING COMMISSION
EXHIBIT A
CITY OF TEMECULA
REVISED FINAL CONDITIONS OF APPROVAL
Planning Application No PLANNING APPLICATION NO 01 0230 TENTATIVE
TRACT MAP NO 29353 REVISED PER PA06 0053
MAJOR MODIFICATION
Project Description The subdivision of 804 7 acres into 39 lots and 8 street
lots which conform to the Planning Areas of the
Roripaugh Ranch Specific Plan
Expiration Date
957 130 001 and 002 957 340 001 003 007 008 and
958 260 001 and 002
November 26 2002 REVISED MAY 17 2006
November 26 2004 REVISED MAY 17 2008
Assessor s Parcel Nos
Approval Date
PLANNING DIVISION
General Requirements
1 The tentative subdivision shall comply with the State of California Subdivision Map Act
and to all the requirements of the Temecula Subdivision Ordinance unless modified by
the conditions listed below A time extension may be approved in accordance with the
State Map Act and City Ordinance upon written request if made 30 days prior to the
expiration date
2 The permittee applicant shall indemnify protect and hold harmless the City and any
agency or instrumentality thereof andor any of its officers employees and agents from
any and all claims actions or proceedings against the City or any agency or
instrumentality thereof or any of its officers employees and agents to attack set aside
void annul or seek monetary damages resulting from an approval of the City or any
agency or instrumentality thereof advisory agency appeal board or legislative body
including actions approved by the voters of the City concerning the Planning Application
which action is brought within the appropriate statute of limitations period and Public
Resources Code Division 13 Chapter 4 Section 21000 et seq including but not by the
way of limitations Section 21152 and 21167 The City shall promptly notify the
permittee applicant of any claim action or proceeding brought forth within this time
period The City shall estimate the cost of the defense of the action and applicant shall
deposit said amount with the City City may require additional deposits to cover
anticipated costs City shall refund without interest any unused portions of the deposit
once the litigation is finally concluded Should the City fail to either promptly notify or
cooperate fully permittee applicant shall not thereafter be responsible to indemnify
defend protect or hold harmless the City any agency or instrumentality thereof or any
of its officers employees or agents Should the applicant fail to timely post the required
deposit the Director may terminate the land use approval without further notice to the
applicant
G PIanning2006 PA06Q053 Roripangh SP Tract Maps Major ModlPlanningIMap 29353 Rev Final COAs 5 06 doc
1
r
3 This project and all subsequent projects within this site shall be consistent with Specific
Plan No 11 the Roripaugh Ranch Specific Plan
4 The project and all subsequent projects within this site shall comply with all mitigation
measures identified within the Final Environmental Impact Report for the Roripaugh
Ranch Specific Plan and the approved Mitigation Monitoring Program thereof
5 Within thirty 30 days of the final approval of the project by the City Council the
tentative map shall be submitted to the Planning Department in final form for review and
approval It shall include all conditions of approval and all modifications made by the
Planning Commission and City Council Amended by the Planning Commission on
1030 02
6 The approval granted by this Resolution shall become effective upon the Effective Date
of the Development Agreement as the term Effective Date is defined in the
Development Agreement adopted concurrently with this Resolution
7 If Subdivision phasing is proposed a ohasina olan shall be submitted to and approved
by the Planning Director
8 The project and all subsequent projects within this site shall be subject to Roripaugh
Ranch Development Agreement PA99 0299
9 AC pavement shall be provided at intersections and approaches at all existing roads
Added by the Planning Commission on 1030 02
Prior to Issuance of Grading Permits
10 A copy of the grading plans shall be submitted and approved by the Planning Division
11 The applicant shall comply with the provisions of Chapter 8 24 of the Temecula
Municipal Code Habitat Conservation by paying the appropriate fee set forth in that
ordinance or by providing documented evidence that the fees have already been paid
12 Prior to the City approval of the grading plans or any other plans requiring MWD
clearance that may impact their property and easement the developer is responsible to
provide the City with MWD s clearance for the said plans
Prior to Recordation of the Final Map
13 The following shall be submitted to and approved by the Planning Division
a A copy of the Final Map
b A copy of the Environmental Constraint Sheet ECS with the following notes
i This property is located within thirty 30 miles of Mount Palomar
Observatory All proposed outdoor lighting systems shall comply with the
California Institute of Technology Palomar Observatory
recommendations Ordinance No 655
G Planning2006 PA06 0053 Roripangh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
2
ii The Roripaugh Ranch Environmental Impact Report EIR was prepared
for this project and is on file at the City of Temecula Community
Development Department Planning Division
iii Lots 31 32 and 33 shall be designated as permanent open space
c A copy of the Covenants Conditions and Restrictions CC R s
i CC R s shall be reviewed and approved by the Planning Director The
CC R s shall include liability insurance and methods of maintaining open
space recreation areas parking areas private roads exterior of all
buildings and all landscaped and open areas including parkways
ii No lot or dwelling unit in the development shall be sold unless a
corporation association property owner s group or similar entity has been
formed with the right to assess all properties individually owned or jointly
owned which have any rights or interest in the use of the common areas
and common facilities in the development such assessment power to be
sufficient to meet the expenses of such entity and with authority to
control and the duty to maintain all of said mutually available features of
the development Such entity shall operate under recorded CC R s
which shall include compulsory membership of all owners of lots andor
dwelling units and flexibility of assessments to meet changing costs of
maintenance repairs and services Recorded CC R s shall permit
enforcement by the City for provisions required as Conditions of Approval
The developer shall submit evidence of compliance with this requirement
to and receive approval of the city prior to making any such sale This
condition shall not apply to land dedicated to the City for public purposes
iii Every owner of a dwelling unit or lot shall own as an appurtenance to
such dwelling unit or lot either 1 an undivided interest in the common
areas and facilities or 2 a share in the corporation or voting
membership in an association owning the common areas and facilities
iv All future property owners shall agree to be a part of the proposed
Community Facilities District CFD or any other similar financing
mechanism
14 Prior to the City approval of the grading plans improvement plans the final map or any
other plans requiring MWD clearance that may impact their property and easement the
developer is responsible to provide the City with MWD s clearance for the said plans
Prior to Issuance of Building Permits
15 With the exception of lot 22 fire station site no residential building permits shall be
issued for the lots created by this tentative map Amended with PA06 0053 approved
May 17 2006
G Planning2006PA06 0053 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs 5 06 doc
3
PUBLIC WORKS DEPARTMENT
Unless otherwise noted all conditions shall be completed by the Developer at no cost to any
Government Agency
General Conditions
16 It is understood that the Developer correctly shows on the Tentative Map all existing and
proposed easements traveled ways paseos pedestrian trails improvement constraints
detention basins and drainage courses and their omission will subject the project to
further review and may require revision
17 A Grading Permit for mass rough andor precise grading shall be obtained from the
Department of Public Works prior to commencement of any construction outside of the
City maintained road right of way
18 An Encroachment Permit shall be obtained from the Department of Public Works prior to
commencement of any construction within an existing or proposed City right of way An
Encroachment Permit may be issued for all roads designated as private streets
19 The Developer shall participate in a Cooperative Agreement with the County allowing the
City to act on their behalf if at the time prior to issuance of a grading permit in the
County area the annexation process has not been completed
20 The Developer shall submit a Maintenance Agreement to maintain flood control facilities
for the portions of Santa Gertrudis Creek and Long Valley Wash located within the
project site It must be mutually agreeable to the City Director of Public Works
Riverside County Flood Control Water Conservation District RCFCWCD and the
Home Owners Association HOA The Maintenance Agreement shall contain a funding
mechanism whereby all residential dwelling units in the proposed project will be equally
assessed for the Santa Gertrudis Creek and Long Valley Wash maintenance The
Maintenance Agreement shall be executed prior to issuance of the first building permit
21 The Developer shall agree to the formation of a Community Facilities District for the
construction of but not limited to road bridge drainage traffic signal intersection
landscape and fire station improvements in accordance with the Roripaugh Ranch
Specific Plan The form of the Agreement shall be subject to the approval of the City
Engineer and City Attorney and shall be executed prior to final map recordation
22 All easements andor right of way dedications shall be offered for dedication to the
public or other appropriate agency and shall continue in force until the City accepts or
abandons such offers All dedications shall be free from all encumbrances as approved
by the Department of Public Works
23 The Developer shall obtain letters giving permission to grade or easements for any off
site work performed on adjoining properties The letters or easements shall be in a
format as directed by the Department of Public Works
24 The Developer shall make a good faith effort to acquire the required off site property
interests and if he or she should fail to do so the Developer shall prior to submittal of
the Final Map for recordation enter into an agreement to complete the improvements
G PIanning2006 PA06 0053 Roripangh SP Tract Maps Major ModlPIanninglMap 29353 Rev Final COAs 5 06 doc
4
pursuant to the Subdivision Map Act Section 66462 and Section 66462 5 Such
agreement shall provide for payment by the Developer of all costs incurred by the City to
acquire the off site property interests required in connection with the subdivision
Security of a portion of these costs shall be in the form of a cash deposit in the amount
given in an appraisal report obtained by the Developer at the Developer s cost The
appraiser shall have been approved by the City prior to commencement of the appraisal
25 A development phasing plan addressing the schedule of necessary infrastructure
requirements shall be approved by the Department of Public Works and the Planning
Director prior to approval of any subsequent application
26 The Developer shall pay to the City the Public Facilities Development Impact Fee as
required by and in accordance with Chapter 15 06 of the Temecula Municipal Code and
all Resolutions implementing Chapter 15 06
27 All utility systems such as electric including those which provide direct service to the
project site andor currently exist along public rights of ways adjacent to the site except
electrical lines rated 33 kv or greater gas telephone water sewer and cable TV shall
be placed underground with easements provided as required and designed and
constructed in accordance with City Codes and the utility provider
Circulation
28 Adequate primary and secondary access shall be provided for each phase of
development as approved by the Department of Public Works Vehicular access
easements shall be secured across undeveloped areas to provide secondary access
The exact location and number of access points shall be subject to review and approval
by the Department of Public Works at the time of submittal of future individual tentative
tract maps andor development applications Additional right of way at entries may be
required to provide for turning lanes as directed by the Department of Public Works
29 Access along Murrieta Hot Springs Road Butterfield Stage Road Nicolas Road and the
Loop Roads as shown on this master tentative tract map shall be restricted except at
street intersections and driveways to be identified in individual tentative tract maps and
approved by the Department of Public Works
30 All street sections shall correspond with the Roripaugh Ranch Specific Plan Figures 2 4
2 4A 2 5 2 5A and 2 5A 1 and by reference made a part of these conditions of
approval typical roadway cross sections and requirements of the Circulation Element of
the City s General Plan and City ordinances and standards
31 The Developer shall obtain permission from adjacent affected property owners along
Nicolas Road and Butterfield Stage Road to allow for grading and any related driveway
improvements necessary to continue to allow legal vehicular access through the use of
some mechanism approved by the City s Public Works Department including but not
limited to permission to grade offsite letters blanket or specific right of entry letters and
temporary construction easements
32 Prior to approval of the street improvement plans the developer shall demonstrate that
adequate sight distance at intersections and approved driveways meet City and Caltrans
standards to the satisfaction of the City Engineer
G Planning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs 5 06 doc
5
33 Bridge structure type shall be approved by the City Public Works Department and
Riverside County Flood Control and Water Conservation District Proposed bridges
shall provide acceptable crossing over waterways to accommodate all necessary
vehicular pedestrian equestrian dry and wet utilities future utilities including but not
limited to conduit for fiber optic cable or traffic signal interconnect if not placed within
street pavement The bridge design shall include but not be limited to the following
studies foundation analysis scour analysis and protection measures
34 The Developer shall submit to the City Public Works Department for review and approval
street improvement plans signing and striping plans traffic signal plans and traffic
control plans for all improvements in the phasing section of these conditions
Traffic Mitigation Monitoring Program
35 The Traffic Mitigation Monitoring Program proposes that a traffic study be approved prior
to the issuance of the first building permit for each additional phase of development The
intent of the Traffic Mitioation Monitorino Proaram is not to re define mitiaation
responsibililbutrather to assist in the refinement of area imorovement needs and the
Jiminlof the imorovements The traffic study would 1 document ambient traffic volumes
conditions 2 estimate trip generation for the particular development phase and 3
assess traffic conditions with the traffic added by the particular development phase The
exact study area to be addressed in each of the traffic studies should be defined through
discussions with the City Traffic Engineer In general the study area should include the
immediate access intersections and roadways which would serve the new development
phase and those critical off site intersections and roadways that will provide orimall
access to the new development Critical intersectionsroadways are defined as those
facilities that are experiencing high levels of peak period traffic congestion at the time
the traffic study is to be performed The traffic study findings would assist the City in
proactively planning for area roadway improvements
36 Ensuing Traffic Reports analyzing traffic impacts associated with subsequent
development stages of the Specific Plan shall be submitted to identify implementation
and timing of the necessary improvements to mitigate cumulative traffic impacts
Drainage
37 The Developer shall as required by the City and Riverside County Flood Control and
Water Conservation District protect downstream properties from damages caused by
alteration of the drainage patterns including concentration or diversion of flow and
increases in flow and or velocity Protection shall be provided by constructing adequate
channel improvements drainage facilities and by securing drainage easements as
necessary
38 Drainage and flood control facilities shall be provided in accordance with the
requirements of the City andor Riverside County Flood Control and Water Conservation
District RCFC WCD All drainage facilities shall be designed to convey 100 year
storm flows subject to the approval of the Department of Public Works and
RCFC WCD as applicable
39 Prior to issuance of a grading permit affecting the creek areas the Developer shall
submit a Drainage Management Plan covering both Santa Gertrudis Creek and Long
G PIanning2006 PA06 0053 Roripangh SP Tract Maps Major ModIPlnnninglMap 29353 Rev Final COAs 5 06 doc
6
Valley Wash to the City and RCFC WCD to review the adequacy of the proposed and
existing downstream drainage facilities The Drainage Management Plan will address
how the planned improvements will prevent downstream erosion and flooding impacts
40 Prior to issuance of the first building permit the Developer shall provide a flood control
Maintenance Agreement for the portions of Santa Gertrudis Creek and Long Valley
Wash within the project site It must be mutually agreeable to the City Department of
Public Works the Riverside County Flood Control and Water Conservation District and
the homeowners association This agreement shall state that the City is only
responsible for maintaining flood control facilities under public roads and is not
responsible for maintaining the Santa Gertrudis Creek and Long Valley Wash channels
or detention basins
41 The Developer shall construct the proposed on and offsite drainage facility
improvements and interim detention basins andor flow by basins as recommended in
the Specific Plan and Drainage Study documents andor as directed by the Department
of Public Works and RCFC WCD as applicable
42 Prior to issuance of grading permits the Developer shall identify and design as
necessary interim channel improvements including but not limited to grading and
construction of detention basins before permanent channel improvements are
constructed
43 Drainage facilities within each phase shall be constructed immediately after the
completion of the site grading and prior to or concurrently with the initial site
development within that phase
44 The Developer shall accept and properly dispose of all off site drainage flowing onto or
through the site The Developer in procuring the protection of downstream properties
has elected to construct two detention basins in the Plateau Area a detention basin in
Santa Gertrudis Creek and a flow by basin in Long Valley Wash These detention and
flowby basins shall be adequately sized so as not to increase the flow and velocities
exiting the project boundary
45 The Developer shall provide adequate bank protection as approved by the City
Department of Public Works and RCFC WCD to allow a bridge crossing at Nicolas
Road Calle Girasol along Santa Gertrudis Creek Nicolas Road will not be accepted into
the City s maintained street system until all offsite channel improvements are complete
and accepted by the City and RCFC WCD
46 The Developer shall provide maintenance roads to all proposed detention basins to
provide access for maintenance Road specifications such as width and type shall be
per Riverside County Flood Control and Water Conservation District requirements
47 Prior to issuance of grading permits the Developer shall coordinate any construction
that could impact Metropolitan Water District MWD facilities to assure that their
facilities are not damaged by project construction either on site or offsite
48 The City reserves the right to require the developer to mitigate any concentrated offsite
flows and to adequately disperse them by the use of rip rap or equivalent improvements
G Planningl2006PA06 0053 Roripaugh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
7
as approved by and to the satisfaction of the City Engineer This condition shall be in
force during the entire development process for the project
49 A Flood Plain Development Permit and Flood Study shall be submitted to the
Department of Public Works for review and approval The flood study shall be in a
format acceptable to the Department and include but not be limited to the following
criteria
a Drainage and flood protection facilities which will protect all structures by
diverting site runoff to streets or approved storm drain facilities
b Adequate provision shall be made for the acceptance and disposal of surface
drainage entering the property from adjacent areas
c Identify and mitigate impacts of grading to any adjacent floodway or floodplain
d The location of existing and post development 1 DO year floodplain and floodway
50 Prior to issuance of a grading permit in the floodplain the Developer shall provide a
Conditional Letter of Map Revision CLOMR or equivalent Federal Emergency
Management Agency FEMA application and comply with that process
51 Prior to issuance of occupancy permits in those lots adjacent to either Santa Gertrudis
Creek or Long Valley Wash the Developer shall submit appropriate documentation to
the Federal Emergency Management Agency and obtain approval of Letter of Map
Revision LOMR
52 A flood mitigation charge shall be paid prior to issuance of grading permits The Area
Drainage Plan fee is payable to the Riverside County Flood Control and Water
Conservation District by either cashier s check or money order prior to issuance of
permits based on the prevailing area drainage plan fee If the full Area Drainage Plan
fee or mitigation charge has already been credited to this property no new charge needs
to be paid
Water and Sewer
53 Water and sewer facilities shall be installed in accordance with the requirements and
specifications of the City Eastern Municipal Water District EMWD and Rancho
California Water District RCWD Such requirements shall be applied at the subdivision
or plot plan stages of the development
54 Prior to the approval of subsequent development applications the Developer shall
comply with the Water Master Plan to EMWD and RCWD to check for adequacy of the
proposed water facilities The Developer shall obtain written approval for the water
system from EMWD and RCWD
55 Prior to the approval of subsequent development applications the Developer shall
comply with the Sewer Master Plan to EMWD to check for adequacy of the proposed
sewer facilities The Developer shall obtain written approval for the sewer system from
EMWD
56 Prior to approval of the final map the developer shall provide the City with adequate
documentation from the local water purveyors EMWD and RCWD that they have
G Planning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final CQAs 5 06 doc
8
adequate water supplies to serve project start up through completion and full occupancy
according to the requirements of Senate Bills 221 and 610
57 The Developer shall install reclaimed water lines on the major road network to irrigate
landscaped areas to the satisfaction of the Public Works and Temecula Community
Services Departments if tilrsll jllsllt tAs sallrss sf gsvsls msAt BAg llAtil slleA tims tAs
pmjest is e8FAf lets reslaimect a atsr iRes S8S8mB a Jailaels vitlliA 299 feet sf aFlY
rejsst ballAgary reclaimed water is to be available to the site prior to the
construction of these roads or it is anticipated to be available in the near term
Amended by the City Council on 11 262002
Grading
58 Prior to the issuance of any grading permit the Developer shall receive written clearance
from the following agencies State of California Department of Fish and Game U S
Army Corps of Engineers and U S Fish and Wildlife Service Where appropriate the
terms conditions and recommendations of the noted agencies shall be incorporated as
Conditions of Approval into the areas of development
59 No grading shall be permitted for any development area prior to tentative map approval
60 Grading plans and operations shall be in accordance with the California Building Code
City Grading Standards the recommendations contained in the Geotechnical Report or
any subsequent reports prepared for the project the conditions of the grading permit
and accepted grading construction practices and the recommendations and standards
specified in the Specific Plan and Environmental Impact Report EIR documents
61 Prior to issuance of any grading permit erosion control plans shall be prepared in
conformance with applicable City Standards and subject to approval by the Department
of Public Works The Developer shall post security and enter into an agreement
guaranteeing the grading and erosion control improvements
62 The Developer shall comply with the requirements of the National Pollutant Discharge
Elimination System NPDES permit regulated by the State Water Resources Control
Board and the Storm Water Pollution Prevention Plan SWPPP implemented by the
San Diego Regional Water Quality Control Board No grading shall be permitted until an
NPDES Notice of Intent NOI has been filed or the project is shown to be exempt
63 The Developer shall post a clearly visible sign at the intersection of Nicolas Road and
Calle Girasol to notify residents of the Nicolas Valley if and when blasting will occur at
least two days prior to scheduled blasting Any blasting activities will be limited to the
hours of 9 AM to 4 PM Monday through Friday Prior to blasting the Developer shall
obtain permission from the City Engineer to post notice in at least one newspaper of
local circulation at least one week in advance
64 Prior to issuance of grading permits the Developer shall submit a Dust Control Plan
DCP to SCAQMD that is consistent with Rule 403 guidelines for approval The
Developer shall submit written proof to the City that SCAQMD has reviewed and
approved the DCP The DCP shall be applicable for all onsite as well as offsite work
and includes but is not limited to the following activities twice daily soil watering street
sweeping covering of trucks hauling soil away chip sealing access roads hydroseeding
G Planning2OO61PA06 Q053 Roripaugh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
9
exposed soil surfaces and adding chemical binders or surfactants to water used for
watering Also the Developer shall provide the City with documentation that appropriate
construction equipment that is anticipated to be used for more than 30 days has had
tune ups or equivalent work to assure low NOX emissions In addition all diesel
equipment and vehicles must be equipped with particulate filters and use only low sulfur
fuels
65 Prior to issuance of grading and building permits the individual contractors shall submit
a Traffic Management Plan TMP to the Public Works Department that includes but is
not limited to scheduling receipt of construction materials to off peak travel periods
routing construction traffic through areas of least impact sensitivity limiting lane closures
and detours to off peak travel periods and staging areas away from existing residential
uses
66 Prior to issuance of a grading permit the Developer shall prepare and file a Noise
Control Plan NCP with the Public Works Department The NCP will be generally
consistent with the mitigation monitoring program and the City s construction noise
ordinance
67 Graded but undeveloped land shall be maintained weed free and planted with interim
landscaping such as hydroseed and temporary irrigation within ninety days of
completion of grading unless building permits are obtained
68 Paleontologists and Archeologists shall be present during grading including excavated
soil stockpiles in accordance with the Environmental Impact Report mitigation measure
69 An importexport route shall be submitted to the Department of Public Works prior to
issuance of any grading permit The plan shall include limitation to the dura ion of the
grading operation and construction activities a Traffic Control Plan and a daily time
schedule of operations
70 A Soils Report shall be prepared by a registered Civil or Soils Engineer and submitted to
the Department of Public Works with the initial grading plan check The report shall
address all soils conditions of the site and provide recommendations for the
construction of engineered structures and preliminary pavement sections
71 A Geotechnical Report shall be prepared by a registered engineer or engineering
geologist and submitted to the Department of public Works with the initial grading plan
check The report shall address special study zones and identify any geotechnical
hazards for the site including location of faults and potential for liquefaction and
landsides The report shall include recommendations to mitigate the impact of ground
shaking and liquefaction
72 If subsequent Geotechnical and Soils Reports determine that dewatering of the site is
necessary during construction necessary permits ie in compliance with NPDES permit
shall be obtained from appropriate agencies prior to approval of the grading plans
73 All public streets shall be maintained and cleaned if necessary on a daily basis during
grading operation and construction activities Cash deposit letter of credit or posting of
bond to guarantee maintenance of all public rights of way affected by the grading
G Planningl2006PA06 0053 Roripaugh SP Tract Maps Major ModPIanningIMap 29353 Rev Fmal COAs 5 06 doc
10
operations and construction activities shall be posted prior to issuance of grading
permits
Specific Plan Phasing
74 Construction of the development permitted by the Specific Plan including recordation of
subdivision maps may be carried out in stages provided that adequate vehicular access
is constructed for all dwelling units in each stage of development and further provided
that such development conforms substantially with the intent and purpose of the Specific
Plan Conceptual Phasing Plan Figure 2 10 and Phasing of Road Improvements Section
2 2 6
75 In the event that the City is unable to construct the street and slopes acquire the
additional right of way and complete any related proceedings associated with that
process for the segment on Butterfield Stage Road from Chemin Clinet to Rancho
California Road by the 510th building permit the Developer shall be responsible for
completing this work by the 510 h building permit
76 Prior to the issuance of the designated number of building permits for each phase the
developer or the CFD must construct the improvements identified below The City may
require additional or supplemental traffic studies prior to approval of future tentative tract
maps If these studies confirm that area intersections are operating below LOS D or
otherwise pose an unsafe condition then the developer shall be responsible for
mitigating these conditions in addition to the mitigation measures already identified in
the EIR
SPECIFIC PLAN PHASE 1
a ONSITE ROAD IMPROVEMENTS
Prior to issuance of the 34th building permit the following improvements shall be
completed
i Secondary Access Provide secondary access from Lots 1 3 4 6 7 to
Murrieta Hot Springs Road
Prior to issuance of the 108th building permit the following improvements shall be
completed
ii Improve Murrieta Hot Springs Road from existing improvements east of
Pourroy Road to the MWD Easement Specific Plan Arterial Highway
110 R1W to include dedication of full width street right of way installation
of full width street improvements paving curb and gutter sidewalk street
lights drainage facilities signing and striping utilities including but not
limited to water and sewer and a 14 foot wide raised landscaped median
All proposed improvements shall be coordinated with existing
improvements including raised landscaped median and lane width
transitions as approved by the City Traffic Engineer
iii Improve Murrieta Hot Springs Road from the MWD Easement to Butterfield
Stage Road Specific Plan Modified Arterial Highway 110 R1W to
include dedication of full width street right of way installation of half width
street improvements including a 14 foot wide raised landscaped median
and a 14 foot wide travel lane adjacent to the median on the unimproved
half paving curb and gutter sidewalk street lights drainage facilities
G Planning2006 PA06 00S3 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs 5 06 doc
11
signing and striping and utilities including but not limited to water and
sewer Driveways shall be constructed to provide access to the MWD
property and easement
iv Improve Butterfield Stage Road from Nicolas Road to Murrieta Hot Springs
Road Specific Plan Augmented Arterial Highway 122 R1W to include
dedication of full width street right of way installation of half width street
improvements plus a 14 foot wide raised landscaped median and a 12 foot
travel lane adjacent to the median on the unimproved half paving curb
and gutter sidewalk street lights drainage facilities signing and striping
and utilities including but not limited to water and sewer
v Dedicate full width right of way on Butterfield Stage Road from Murrieta
Hot Springs Road to the northern project boundary Specific Plan Arterial
Highway 110 R1W
vi Improve Butterfield Stage Road from Nicolas Road to the southern project
boundary Specific Plan Arterial Highway 110 R1W to include dedication
of full width street right of way installation of half width street
improvements including a 14 foot wide raised landscaped median and a
14 foot wide travel lane adjacent to the median on the unimproved half
full width bridge structures over Santa Gertrudis Creek and Long Valley
Wash paving curb and gutter sidewalk street lights drainage facilities
signing and striping and utilities including but not limited to water and
sewer
vii Improve Nicolas Road from Butterfield Stage Road to the western project
boundary Specific Plan Modified Secondary Highway 110 R1W to
include dedication of full width street right of way installation of the
northerly half width plus 10 feet of street improvements including paving
curb and gutter sidewalk soft surface path split rail fence street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
viii Improve South Loop Road from Butterfield Stage Road to the end of the
fire station site frontage Specific Plan Modified Principal Collector Road
76 R1W to include dedication of full width street right of way installation
of the southerly half width plus 6 feet of street improvements including
paving curb and gutter sidewalk street lights drainage facilities signing
and striping and utilities including but not limited to water and sewer
Prior to issuance of the 400 h building permit the following improvements shall be
completed
ix Improve P Street along Lot 8 frontage Specific Plan Modified Collector
Road 66 R1W to include dedication of full width street right of way
installation of full width street improvements including paving curb and
gutter sidewalk street lights drainage facilities signing and striping and
utilities including but not limited to water and sewer
x Improve North Loop Road from Butterfield Stage Road to the east side of
Santa Gertrudis Creek Specific Plan Modified Principal Collector Road
76 R1W to include dedication of full width street right of way installation
of full width street improvements including a full width bridge over Santa
Gertrudis Creek paving curb and gutter sidewalk street lights drainage
G P1anning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
12
facilities signing and striping and utilities including but not limited to
water and sewer
b OFFSITE ROAD IMPROVEMENTS
Prior to issuance of the 108th building permit the following improvements shall be
completed
i Improve Nicolas Road from the western project boundary to 450 feet east
of the existing Nicolas Road Calle Girasol intersection Specific Plan
Modified Secondary Road 110 RW Section K to include installation of
40 foot width on center improvements paving asphalt concrete berm
including signing and striping utilities including but not limited to water
and sewer and a 6 foot wide curb separated asphalt concrete path on
the north side
ii The Developer shall obtain permission from adjacent affected property
owners to allow for grading and any related driveway improvements
necessary to continue to allow legal vehicular access onto Nicolas Road
through the use of some mechanism approved by the City s Public Works
Department including but not limited to permission to grade offsite
letters blanket or specific right of entry letters and temporary
construction easements
iii Provide secondary access by constructing improvements for one of the
following options
a If Nicolas Road is designated as the secondary access route the
following improvements shall be completed
i Construct 40 foot on center improvements Specific Plan
Modified Secondary Road 110 RW Section K from 450
feet east of the existing Nicolas RoadCalle Girasol
intersection to Leifer Road including paving asphalt
concrete berm including signing and striping utilities
including but not limited to water and sewer and the full
width bridge structure over and within Santa Gertrudis
Creek
ii Realign existing Calle Girasol to its ultimate intersection
with Nicolas Road including right of way acquisition
iii The Developer shall provide adequate bank protection as
approved by the City Department of Public Works and
RCFC WCD to allow a bridge crossing at Nicolas
Road Calle Girasol along Santa Gertrudis Creek Nicolas
Road will not be accepted into the City s maintained street
system until all offsite channel improvements are complete
and accepted by the City and RCFC WCD
b If Calle Chapos from Butterfield Stage Road to Walcott Lane and
Calle Chapos to Calle Girasol from Walcott Lane to the existing
Nicolas Road Calle Girasol intersection is designated as
secondary access the following improvements shall be
completed
G Planning2006 PA06 0053 Roripangh SP Tract Maps Major ModIPlanninglMap 29353 Rev Final COAs 5 06 doc
13
i Construct 38 foot width on center improvements Specific
Plan Modified Collector Road 66 R1W Section L from
Butterfield Stage Road to the Nicolas Road Calle Girasol
intersection including paving and signing and striping
ii Provide horizontal realignment and right of way
acquisition as required by the City Fire Chief and City
Engineer from Walcott Lane to the existing Nicolas
Road Calle Girasol intersection
c If Butterfield Stage Road Specific Plan Arterial Highway 110
R1W is designated as secondary access construct half width
improvements from the southern project boundary to Chimen
Clinet including dedication of full width street right of way
installation of half width street improvements including a 14 foot
wide raised landscaped median and a 14 foot wide travel lane
adjacent to the median on the unimproved half paving curb and
gutter sidewalk street lights drainage facilities signing and
striping and utilities including but not limited to water and sewer
excluding any existing improvements
c TRAFFIC SIGNALS WITHOUT A DEVELOPMENT AGREEMENT
The developer must make a fair share contribution towards the improvement of
the following intersections identified below The improvements listed below are
in addition to the existing improvements and lane configurations and shall
supplement but not replace existing turning movements Additional or
supplemental traffic studies shall be conducted prior to approval of future
tentative tract maps If these studies confirm that these intersections are
operating below LOS D or otherwise pose an unsafe condition then the
developer shall be responsible for mitigating these conditions in addition to the
mitigation measures already identified in the EIR
Prior to issuance of the 1 st building permit in Lots 1 7 8 and 22
i 1 15 Freeway Southbound Ramps at Rancho California Road
southbound leftturn lane southbound free right turn lane westbound free
right turn lane and eastbound free right turn lane
ii 1 215 Freeway Southbound Ramps at Murrieta Hot Springs Road
southbound left turn lane southbound right turn lane eastbound through
lane eastbound right turn lane westbound through lane and westbound
free right turn lane
iii Ynez Road at Winchester Road southbound right turn overlap
iv Ynez Road at Rancho California Road eastbound through lane
v North General Kearney Road at Nicolas Road traffic signal
vi Butterfield Stage Road at Rancho California Road traffic signal
vii Murrieta Hot Springs Road at Alta Murrieta lane improvements as yet
undetermined The developer shall provide the City of Temecula with a
letter from the City of Murrieta stating that a fair share contribution to
identified improvements at this intersection has been made
G Planning2006PA06 0053 Roripangh SP Tract Maps Major ModIPlanninglMap 29353 Rev Final COAs 5 06 doc
14
viii Murrieta Hot Springs Road at Pourroy Road construct traffic signal and
related intersection improvements as warranted
d TRAFFIC SIGNALS WITH A DEVELOPMENT AGREEMENT
The developer must bond and construct or make a fair share contribution
towards the improvement of the following intersections identified below The
improvements listed below are in addition to the existing improvements and lane
configurations and shall supplement but not replace existing turning movements
Additional or supplemental traffic studies shall be conducted prior to approval of
future tentative tract maps
Prior to issuance of the 1 sl building permit in Lots 1 7 8 and 22
i 1 215 Freeway Southbound Ramps at Murrieta Hot Springs Road
southbound left turn lane southbound right turn lane eastbound through
lane eastbound right turn lane westbound through lane and westbound
free right turn lane
ii North General Kearney Road at Nicolas Road traffic signal
iii Butterfield Stage Road at Rancho California Road traffic signal
iv Murrieta Hot Springs Road at Alta Murrieta lane improvements as yet
undetermined The developer shall provide the City of Temecula with a
letter from the City of Murrieta stating that a fair share contribution to
identified improvements at this intersection has been made
v Murrieta Hot Springs Road at Pourroy Road construct traffic signal and
related intersection improvements as warranted
e WATER IMPROVEMENTS
i Install water mains per Eastern Municipal Water District requirements
ii The Developer shall install reclaimed water lines to irrigate landscaped
areas to the satisfaction of the Public Works and Temecula Community
Services Departments if throughout the course of development and until
such time the project is complete reclaimed water lines become available
within 300 feet of any project boundary
f SEWER IMPROVEMENTS
i Install sewer main in Murrieta Hot Springs Road west of pourroy Road
ii Install sewer main in Nicolas Road per Eastern Municipal Water District
requirements
g DRAINAGE IMPROVEMENTS
i Construct detention basin west of Lot 1 and detention basin south of Lot 5
along southern Plateau area
ii Construct storm drains and related outlet facilities as required by the
hydrology hydraulics studies
SPECIFIC PLAN PHASE 2
Prior to issuance of the 510th building permit or any building permit in Phase 2 the
following improvements must be completed
G Planning2006 PA06 0053 Roripangh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
15
a ONSITE ROAD IMPROVEMENTS
i Improve Murrieta Hot Springs Road from the MWD Easement to Butterfield
Stage Road Specific Plan Modified Arterial Highway 110 R1W to
include installation of remaining half width street improvements paving
curb and gutter sidewalk street lights drainage facilities signing and
striping utilities including but not limited to water and sewer A 14 foot
wide raised landscaped median shall be constructed in Phase 1
ii Improve Butterfield Stage Road from Murrieta Hot Springs Road to Nicolas
Road Specific Plan Augmented Arterial Highway 122 R1W to include
installation of remaining half width street improvements paving curb and
gutter sidewalk street lights drainage facilities signing and striping and
utilities including but not limited to water and sewer A 14 foot wide
raised landscaped median shall be constructed in Phase 1
iii Improve Butterfield Stage Road from Nicolas Road to the southern project
boundary Specific Plan Arterial Highway 110 R1W to include
installation of remaining half width improvements including installation of
paving curb and gutter sidewalk street lights drainage facilities signing
and striping utilities including but not limited to water and sewer A 14
foot wide raised landscaped median shall be constructed in Phase 1
iv Construct or bond for grading and full width improvements on Butterfield
Stage Road from Murrieta Hot Springs Road to the northern project
boundary Specific Plan Arterial Highway 110 R1W to include
installation of full width street improvements including a 14 foot wide
raised landscaped median paving curb and gutter sidewalk street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
v Improve North Loop Road and South Loop Road Specific Plan Modified
Principal Collector Road 76 R1W to include dedication of full width
street right of way installation of full width street improvements
construction of a full width bridge over Long Valley Wash raised
landscaped median paving curb and gutter sidewalk street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
vi Improve Nicolas Road from Butterfield Stage Road to the western project
boundary Specific Plan Modified Secondary Highway 110 R1W Section
D to include remaining southerly half width street improvements including
paving curb and gutter sidewalk soft surface path split rail fence street
lights drainage facilities signing and striping and utilities including but
not limited to water and sewer
vii Improve P Street from the southern boundary of Lot 8 to Butterfield Stage
Road Specific Plan Modified Collector Road 66 R1W to include
dedication of full width street right of way installation of full width street
improvements including paving curb and gutter sidewalk street lights
drainage facilitiEls signing and striping and utilities including but not
limited to water and sewer
viii Improve E Street from P Street to Nicolas Road Specific Plan Modified
Collector Road 66 R1W to include dedication of full width street right of
G PlanningI2006PA06 0053 Roripaugh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
16
way installation of full width street improvements including paving curb
and gutter sidewalk street lights drainage facilities signing and striping
and utilities including but not limited to water and sewer
b OFFSITE ROAD IMPROVEMENTS
i Improve Butterfield Stage Road from the southern project boundary to
Rancho California Road excluding existing improvements Specific Plan
Arterial Highway 110 R1W to include installation of full width
improvements except sidewalk on the County side paving curb and
gutter sidewalk street lights drainage facilities signing and striping
utilities including but not limited to water and sewer and a 14 foot wide
raised landscaped median
ii Improve Nicolas Road from 450 feet east of the Nicolas RoadCalle
Girasol intersection to Leifer Road Specific Plan Modified Secondary
Road 110 R1W Section K to include dedication of full width street
right of way installation of 40 foot width improvements including full width
bridge improvements at Santa Gertrudis Creek paving asphalt concrete
berm signing and striping utilities including but not limited to water and
sewer and a curb separated asphalt concrete path along the northerly
side
ili Improve Calle Chapos from Butterfield Stage Road to Walcott Lane
Specific Plan Modified Collector Road 66 R1W Section L to include
installation of 38 foot on center improvements to include paving asphalt
concrete berm signing and striping utilities including but not limited to
water and sewer
iv Realign existing Calle Girasol to its ultimate intersection with Nicolas
Road including right of way acquisition
c TRAFFIC SIGNALS WITHOUT A DEVELOPMENT AGREEMENT
The developer must make a fair share contribution towards the improvement of
the following intersections identified below Additional or supplemental traffic
studies shall be conducted prior to approval of future tentative tract maps If
these studies confirm that these intersections are operating below LOS D or
otherwise pose an unsafe condition then the developer shall be responsible for
mitigating these conditions in addition to the mitigation measures already
identified in the EI R
Prior to issuance of the 1 sl building permit in Phase 2 as defined in the Specific
Plan
i Butterfield Stage Road and Nicolas Road North Loop Road construct
traffic signal and related intersection improvements as warranted
ii Butterfield Stage Road and Calle ChaposSouth Loop Road construct
traffic signal and related intersection improvements as warranted
iii Murrieta Hot Springs Road and Butterfield Stage Road construct traffic
signal and related intersection improvements as warranted
iv La Serena Way and Meadows Parkway construct traffic signal and
related intersection improvements as warranted
G PlanningI2006PA06 0053 Roripangh SP Tract Maps Major ModPlanningIMap 29353 Rev Final COAs 5 06 doc
17
v 1 15 Freeway Southbound Ramps at Winchester Road southbound left
turn lane southbound right turn lane westbound through lane westbound
free right turn lane eastbound through lane and eastbound free right turn
lane
vi 1 15 Freeway Northbound Ramps at Winchester Road northbound left
turn lane northbound free right turn lane westbound through lane and
westbound free right turn lane
vii 1 15 Freeway Northbound Ramps at Rancho California Road
northbound left turn and right turn lanes
viii Ynez Road at Winchester Road southbound left turn lane southbound
right turn overlap and eastbound left turn lane
ix Ynez Road at Rancho California Road westbound left turn lane
westbound right turn lane eastbound through lane southbound through
lane southbound free right turn lane and eastbound free right turn lane
x Margarita Road at Winchester Road eastbound left turn lane southbound
right turn lane westbound right turn lane and southbound right turn
overlap
xi Margarita Road at Rancho California Road northbound and southbound
through lanes southbound right turn lane eastbound left turn lane
eastbound right turn overlap westbound left turn lane northbound right
turn lane and westbound right turn overlap
xii Margarita Road at Murrieta Hot Springs Road northbound shared left
through lane eastbound through lane and westbound through lane
xiii Winchester Road at Nicolas Road northbound left turn lane northbound
free right turn lane westbound left turn lane northbound through lane
southbound left turn lane southbound through lane and eastbound right
turn overlap
xiv Winchester Road at Murrieta Hot Springs Road northbound through lane
southbound through lane and westbound through lane
xv Butterfield Stage Road at Rancho California Road northbound left turn
lane northbound through lane southbound left turn lane southbound
through lane eastbound left turn lane eastbound through lane westbound
left turn lane and westbound through lane
xvi Calle Contento at Rancho California Road eastbound left turn lane
eastbound through lane westbound left turn lane and westbound through
lane
d TRAFFIC SIGNALS WITH A DEVELOPMENT AGREEMENT
The developer must bond and construct or make a fair share contribution
towards the improvement of the following intersections identified below The
improvements listed below are in addition to the existing improvements and lane
configurations and shall supplement but not replace existing turning movements
Additional or supplemental traffic studies shall be conducted prior to approval of
future tentative tract maps
G Planning2006 PA06OO53 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs 5 06 doc
18
Prior to issuance of the 1 sl building permit in Phase 2 as defined in the Specific
Plan
i Butterfield Stage Road and Nicolas Road North Loop Road construct
traffic signal and related intersection improvements as warranted
ii Butterfield Stage Road and Calle ChaposSouth Loop Road construct
traffic signal and related intersection improvements as warranted
iii Murrieta Hot Springs Road and Butterfield Stage Road construct traffic
signal and related intersection improvements as warranted
iv Margarita Road at Murrieta Hot Springs Road northbound shared left
through lane eastbound through lane and westbound through lane
v Winchester Road at Nicolas Road northbound left turn lane northbound
free right turn lane westbound left turn lane northbound through lane
southbound left turn lane southbound through lane and eastbound right
turn overlap
vi Winchester Road at Murrieta Hot Springs Road northbound through
lane southbound through lane and westbound through lane
vii Butterfield Stage Road at Rancho California Road northbound left turn
lane northbound through lane southbound left turn lane southbound
through lane eastbound left turn lane eastbound through lane
westbound left turn lane and westbound through lane
e ONSITE DRAINAGE IMPROVEMENTS
i Install full width box culverts or equivalent drainage facilities where Santa
Gertrudis Creek crosses North Loop Road and Butterfield Stage Road
The drainage facilities shall be designed to convey the tributary 1 DO year
storm flows
ii Install full width box culverts or equivalent drainage facilities where Long
Valley Wash crosses South Loop Road and Butterfield Stage Road The
drainage facilities shall be designed to convey the tributary 1 DO year
storm flows
iii Construct Santa Gertrudis Creek Channel through Lots 33 37 and 38
The channel shall be designed to convey the tributary 100 year storm
flow and have adequate bank hardening and or other treatment to protect
the adjacent properties from flooding
iv Construct the detention basin on Lot 38 The detention basin should be
designed to regulate outflow rate such that the peak flow in Santa
Gertrudis Creek west of Butterfield Stage Road is equal to or less than
the undeveloped condition
v Construct the flow by basin on Lot 34 The flow by basin should be
designed to regulate outflow rate such that the peak flow in Long Valley
Wash west of Butterfield Stage Road is equal to or less than the
undeveloped condition
G Planning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs S 06 doc
19
vi Construct Long Valley Wash through Lots 34 and 35 The channel shall
be designed to convey the tributary 1 DO year storm flow and have
adequate bank hardening andor other treatment to protect the adjacent
properties from flooding
f OFFSITE DRAINAGE IMPROVEMENTS
i Construct Santa Gertrudis Creek Channel from the box culvert or
equivalent drainage facility crossing Butterfield Stage Road westerly to the
confluence with the existing Santa Gertrudis Creek The channel shall be
designed to convey the tributary 1 DO year storm flow have adequate bank
hardening andor other treatment to protect the adjacent properties from
flooding The channel shall be extended a sufficient distance and designed
in a manner that flows will return to the existing conditions at the outlet
point Access roads shall be constructed as necessary to provide
adequate channel maintenance The channel access roads and
confluence structures shall be contained within drainage easements
obtained by the developer
g WATER IMPROVEMENTS
i Install water mains per Eastern Municipal Water District requirements and
per Rancho California Water District requirements as necessary
ii The Developer shall install reclaimed water lines to irrigate landscaped
areas to the satisfaction of the Public Works and Temecula Community
Services Departments if throughout the course of development and until
such time the project road infrastructure is complete by phase reclaimed
water lines become available within 300 feet of any project boundary
h SEWER IMPROVEMENTS
i Install a sewer main in Nicolas Road from Butterfield Stage Road to Leifer
Road and then to Joseph Road where it will connect to an existing 21 inch
sewer line
ii Install sewer mains per Eastern Municipal Water District requirements
and City Standard No 609 Trench shall be per City Standard No 407
which will require the overlay of half of Nicolas Road between Leifer Road
and Joseph Road
COMMUNITY SERVICES DEPARTMENT
General Requirements
77 If any of the following conditions of approval differ from the Specific Plan text or exhibits
the conditions enumerated herein shall take precedent
78 All perimeter slope landscape areas designated as Temecula Community Services
District TCSD maintenance areas shall be identified and offered for dedication to the
TCSD as a maintenance easement on the final map Underlying ownership of the
respective areas shall remain with the individual property owner or the Homeowner s
Association All other landscape areas open space trails entry monumentation
signage pedestrian portals bus shelters pedestrian bridge fences walls and private
gated areas shall be maintained by the Homeowner s Association HOA private
maintenance association or property owner
G PIanning2006 PA06 0053 Roripangh SP Tract Maps Major ModPlanninglMap 29353 Rev Final COAs 5 06 doc
20
79 The current park dedication requirement Quimby for this development is 28 71 acres
based on 2015 single family units This requirement shall be satisfied with the 19 7 acre
community sports park Lot 30 the 5 1 acre neighborhood park Lot 8 and the HOA
owned and maintained recreational areas identified in the Roripaugh Specific Plan
including the private recreation centers Lots 5 and 27 and the private mini park Lot 2
80 The design of the 19 7 acre community sports park Lot 30 and the 5 1 acre
neighborhood park Lot 8 shall be in substantial conformance with the conceptual
designs and guidelines identified within the Specific Plan Prior to submittal of
construction plans the developer shall meet with the Director of Community Services to
determine the location and specifications of the park amenities to be provided on site
Construction plans and specifications must be approved by the Director of Community
Services
81 All park and slope landscape plans submitted for consideration for TCSD maintenance
shall be in conformance with the City of Temecula Landscape and Irrigation
Specifications and Installation Details and the Park Land and Landscape Dedication
Process
82 The design of the 19 7 acre community sports park Lot 30 and the 5 1 acre
neighborhood park Lot 8 shall provide for pedestrian circulation and shall be in
compliance with American with Disabilities Act ADA requirements
83 The developer is entitled to receive a credit against the park and recreation component
of the City s Development Impact Fee DIF pursuant to a Development Agreement or a
DIF Credit Agreement between the applicant and the City prior to approval of the final
map
84 Construction of the 19 7 acre community sports park the 5 1 acre neighborhood park
landscaped medians and proposed TCSD slopelandscape maintenance areas shall
commence pursuant to a pre construction meeting with the developer and TCSD
Maintenance Superintendent Failure to comply with the TCSD review and inspection
process may preclude acceptance of these areas into the TCSD maintenance programs
85 The Home Owner s Association HOA portion of Lot 8 shall be developed concurrently
with the public park portion of Lot 8 The City will not accept the conveyance of the
public park until all improvements have been completed within Lot 8
86 The developer the developer s successor or assignee shall be responsible for all
maintenance of the park sites slopeslandscape areas and landscaped medians until
such time as those responsibilities are accepted by the TCSD or other responsible party
87 The public parks shall be improved and conveyed to the City free and clear of any liens
assessment fees or easements that would preclude the City from utilizing the property
for public purposes A policy of title insurance for the value of the land and the cost of
the improvements and a soils assessment report shall also be provided with the
conveyance of the property
88 The design of the private mini park Lot 2 and the private recreation centers Lots 5 and
27 shall be consistent with the conceptual designs and guidelines identified in the
Roripaugh Specific Plan
G Planning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPlanning Map 29353 Rev Final COAs 5 06 doc
21
I
89 Class II bicycle lanes as specified in the Roripaugh Specific Plan shall be identified on
the street improvements plans and constructed in concurrence with the completion of
said street improvements
90 A multi use trail will be constructed along both sides of Long Valley Wash Lot 35 and
along the north side of Lot 34 If the maintenance roads for the Long Valley Channel are
proposed for this purpose written authorization from RCFCWCD must be provided to
the City allowing public access for trail purposes prior to approval of any tentative map
for the Valley portion If RCFCWCD determines that that the River Walk cannot be
located within the channel right of way then the trail area shall be located outside the
flood control area These trails shall be designed and shown on the respective tentative
map for this area
91 The developer shall dedicate on the final map a fifteen 15 foot easement for public
access within the 30 foot fuel modification zone and construct an multi use trail along the
westerly edge of Lot 22 the southerly edge of Lots 20 21 and 22 and the easterly edge
of Lots 19 and 34
92 All residential street lighting will be maintained by the Home Owner s Association HOA
93 The developer shall contact the City s franchise solid waste hauler for disposal of the
construction debris Only the City s franchisee may haul construction debris
94 The developer shall provide adequate space for a recycling bin within any trash
enclosure in the commercial area Lot 10
Prior to Approval of the Final Map
95 All slope landscape areas intended for dedication to the TCSD for maintenance shall be
identified on each final map by numbered lots with the square footage of said lot
numbers indexed as proposed TCSD maintenance areas
96 Construction drawings for all parks landscaped medians and proposed TCSD
slope landscape maintenance areas shall be reviewed and approved by the Director of
Community Services prior to the approval of the respective final map
97 The developer shall post security and enter into an agreement to improve the public
parks landscaped medians and proposed TCSD slope landscape maintenance areas
prior to the approval of the respective final map
98 An equestrian crossing shall be approved by the Water Quality Control Board WQCB
for the multi purpose trail connection between Lots 19 and 20 across the easterly edge
of Lot 34 prior to the approval of the respective final map
99 The developer shall file a notice of intention with the Temecula Community Services
District to initiate election proceedings for acceptance perimeter slope landscape into the
TCSD maintenance program All costs associated with this process shall be borne by
the developer
G Planning2006 PA06 0053 Roripaugh SP Tract Maps Major ModPIanninglMap 29353 Rev Flnal COAs 5 06 doc
22
Prior to Issuance of Building Permits
100 Prior to issuance of building permits the developer shall provide TCSD verification of
arrangements made with the City s franchise solid waste hauler for disposal of
construction debris
101 The private mini park Lot 2 shall be completed to the satisfaction of the Community
Services Director prior to the issuance of the 100th residential building permit
102 The park portion of the private recreation center Lot 5 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 250th
residential building permit in Lots 1 3 4 6 and 7
103 The building and the pool portion of the private recreation center Lot 5 shall be
completed to the satisfaction of the Community Services Director prior to the issuance of
the 350th residential building permit Lots 1 3 4 6 and 7
104 The 5 1 acre neighborhood park Lot 8 shall be improved including the completion of
the 90 day maintenance period and the conveyance accepted by the City Council prior
to the issuance of the 400 h residential building permit for the overall Roripaugh
Development
105 The Paseo connecting Lot 7 and Lot 8 shall be completed to the satisfaction of the
Community Services Director prior to the issuance or the 400th residential building permit
in Lots 1 3 4 6 and 7
106 The Nature Walk and adjacent landscape areas Lot 36 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 400 h
residential building permit in Lots 1 3 4 6 and 7
107 The 19 7 acre sports park Lot 30 shall be improved including the completion of the 90
day maintenance period and the conveyance accepted by the City Council prior to the
issuance of the 700 h residential building permit for the overall Roripaugh Development
108 The park portion of the private recreation center Lot 27 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 800th
residential building permit for the overall Roripaugh Development
109 The building and the pool portion of the private recreation center Lot 27 shall be
completed to the satisfaction of the Community Services Director prior to the issuance of
the 1150th residential building permit for the overall Roripaugh Development
110 The River Walk and the landscaping adjacent to the maintenance roads on both sides
of Long Valley Wash Lot 35 and along the north side of Lot 34 shall be completed prior
to the issuance of the 700th overall residential building permit in the project
111 If the maintenance road along the north side of Long Valley Wash cannot be used for a
multi use trail a separate trail with landscaping shall be completed to the satisfaction of
the Community Services Director prior to the issuance of the 50th building permit in Lot
26
G PIanning2006PA06 0053 Roripangh SP Trac Maps Major ModIPlanninglMap 29353 Rev Final COAs 5 06 doc
23
112 If the maintenance road along the south side of Long Valley Wash cannot be used for a
multi use trail a separate trail with landscaping shall be completed to the satisfaction of
the Community Services Director prior to the issuance of the 75building permit in Lots
23 24 and 25
113 A pedestrian bridge will be constructed across Long Valley Wash Lot 35 connecting
Lots 24 and 26 to the satisfaction of the Public Works Director and the Community
Services Director prior to the issuance of the 75building permit in Lots 23 24 and 25
114 The developer shall construct a 15 foot soft surface trail within the 30 foot fuel
modification zone to the satisfaction of the Community Services Director along the
westerly edge of Lot 22 the southerly edge of Lots 20 21 and 22 and the easterly edge
of Lots 19 and 34 prior to the issuance of the first building permit in Lots 19 20 and 21
115 Prior to the installation of arterial street lights or issuance of building permits whichever
occurs first the developer shall file an application submit approved Southern California
Edison street light plans and pay the appropriate fees to the TCSD for the dedication of
arterial street lights into the appropriate TCSD maintenance program
Prior to Issuance of Certificates of Occupancy
116 Prior to the issuance of the first certificate of occupancy within each phase map the
developer shall submit the most current list of Assessor s Parcel Numbers assigned to
the final project
117 It shall be the developer s responsibility to provide written disclosure of the existence of
TCSD and its service level rates and charges to all prospective purchasers
FIRE DEPARTMENT
118 Any previous existing conditions for this project will remain in full force and effect unless
superceded by more stringent requirements here
119 Final fire and life safety conditions will be addressed when building plans are reviewed
by the Fire Prevention Bureau These conditions will be based on occupancy use the
California Building Code CBC California Fire Code CFC and related codes which
are in force at the time of building plan submittal
120 The Fire Prevention Bureau is required to set a minimum fire flow for residential land
division per CFC Appendix IIIA Table A III A 1 The developer shall provide for this
project a water system capable of delivering 1500 GPM at 20 PSI residual operating
pressure with a 2 hour duration The required fire flow may be adjusted during the
approval process to reflect changes in design construction type or automatic fire
protection measures as approved by the Fire Prevention Bureau The Fire Flow as
given above has taken into account all information as provided CFC 903 2 Appendix
III A
121 The Fire Prevention Bureau is required to set minimum fire hydrant distances per CFC
Appendix III B Table A III B 1 Standard fire hydrants 6 x 4 x 2 1 2 outlets shall be
located on Fire Department access roads and adjacent public streets Hydrants shall be
spaced at 500 feet apart at each intersection and shall be located no more than 250 feet
G Planning2006 PA06 0053 Roripangh SP Tract Maps Major ModPIanningIMap 29353 Rev Final COAs 5 06 doc
24
from any point on the street or Fire Department access road s frontage to a hydrant
The required fire flow shall be available from any adjacent hydrant s in the system The
upgrade of existing fire hydrants may be required CFC 903 2 9034 2 and Appendix
III B
122 The Fire Prevention Bureau is required to set a minimum fire flow for commercial land
division per CFC Appendix III A Table A III A 1 The developer shall provide for this
project a water system capable of delivering 4000 GPM at 20 PSI residual operating
pressure with a 4 hour duration The required fire flow maybe adjusted during the
approval process to reflect changes in design construction type or automatic fire
protection measures as approved by the Fire Prevention Bureau The Fire Flow as
given above has taken into account all information as provided CFC 903 2 Appendix
III A
123 The Fire Prevention Bureau is required to set minimum fire hydrant distances per CFC
Appendix III B Table A III B 1 Super fire hydrants 6 x 4 x 2 21 2 outlets shall be
located on Fire Department access roads and adjacent public streets Hydrants shall be
spaced at 350 feet apart at each intersection and shall be located no more than 210 feet
from any point on the street or Fire Department access road s frontage to a hydrant
The required fire flow shall be available from any adjacent hydrant s in the system The
upgrade of existing fire hydrants may be required CFC 903 2 9034 2 and Appendix
III B
124 Maximum cul de sac length shall not exceed 1320 feet Minimum turning radius on any
cul de sac shall be thirty seven 37 feet for residential and forty five 45 feet for
commercial CFC 902 2 2 3 CFC 902 2 2 4
125 Private entry driveways with divider medians must be a minimum of 16 feet wide on
each side unless the median is held back 30 feet from face of curb of perpendicular
road
126 If construction is phased each phase shall provide approved access and fire protection
prior to any building construction CFC 8704 2 and 902 2 2 This will include all internal
roads connecting roads between phases and construction gates All required access
must be in and available prior to and during ALL construction Phasing is approved on a
separate map and is ultimately subject to final approval in the field
127 Prior to building construction all locations where structures are to be built shall have
approved temporary Fire Department vehicle access roads for use until permanent
roads are installed Temporary Fire Department access roads shall be an all weather
surface for 80 000 Ibs GVW CFC 8704 2 and 902 2 2 2
128 Prior to building final all locations where structures are to be built shall have approved
Fire Department vehicle access roads to within 150 feet to any portion of the facility or
any portion of an exterior wall of the building s Fire Department access roads shall be
an all weather surface designed for 80 000 Ibs GVW with a minimum AC thickness of
25 feet CFC see 902
129 Fire Department vehicle access roads shall have an unobstructed width of not less than
twenty four 24 feet and an unobstructed vertical clearance of not less than thirteen 13
feet six 6 inches CFC 902 2 2 1
G PIanning2006PA06 0053 Roripangh SP Tract Maps Major ModPIanninglMap 29353 Rev Final COAs 5 06 doc
25
130 Prior to building construction dead end roadways and streets in excess of one hundred
and fifty 150 feet which have not been completed shall have a turnaround capable of
accommodating fire apparatus CFC 902 2 2 4
131 Prior to building construction this development and any street within serving more than
35 homes or any commercial developments shall have two 2 points of access via all
weather surface roads as approved by the Fire Prevention Bureau CFC 902 2 1
132 Prior to issuance of building permits the developer shall furnish one copy of the water
system plans to the Fire Prevention Bureau for approval prior to installation Plans shall
be signed by a registered civil engineer contain a Fire Prevention Bureau approval
signature block and conform to hydrant type location spacing and minimum fire flow
standards After the plans are signed by the local water company the originals shall be
presented to the Fire Prevention Bureau for signatures The required water system
including fire hydrants shall be installed and accepted by the appropriate water agency
prior to any combustible building materials being placed on an individual lot CFC
8704 3 901 2 2 2 and National Fire Protection Association 24 1 4 1
133 Prior to issuance of a Certificate of Occupancy or building final Blue Reflective
Markers shall be installed to identify fire hydrant locations CFC 9014 3
134 All manual and electronic gates on required Fire Department access roads or gates
obstructing Fire Department building access shall be provided with the Knox Rapid entry
system for emergency access by firefighting personnel CFC 9024
Special Conditions
135 Prior to issuance of building permits fuel modification plans shall be submitted to the
Fire Prevention Bureau for review and approval for all open space areas adjacent to the
wildland vegetation interface FC Appendix II A
136 Prior to issuance of building permits plans for structural protection from vegetation fires
shall be submitted to the Fire Prevention Bureau for review and approval The measures
shall include but are not limited to enclosing eaves noncombustible barriers cement or
block walls and fuel modification zones CFC Appendix II A
137 Prior to map recordation the applicant shall submit to the Fire Prevention Bureau a
georectified pursuant to Riverside County standards digital version of the map
including parcel and street centerline information The electronic file will be provided in a
ESRI Arclnfo ArcView compatible format and projected in a State Plane NAD 83
California Zone VI coordinate system The Bureau must accept the data as to
completeness accuracy and format prior to satisfaction of this condition
OTHER AGENCIES
138 Flood protection shall be provided in accordance with the Riverside County Flood
Control District s transmittal dated October 21 2002 a copy of which is attached The
fee is made payable to the Riverside County Flood Control Water District by either a
cashier s check or money order prior to the issuance of a grading permit unless
deferred to a later date by the District based upon the prevailing area drainage plan
fee
G Planning2006 PA06OOS3 Roripaugh SP Tract Maps Major ModP1anning Map 29353 Rev Final COAs 5 06 doc
26
By placing my signature below I confirm that I have read understand and accept all the above
Conditions of Approval I further understand that the property shall be maintained in
conformance with these conditions of approval and that any changes I may wish to make to the
project shall be subject to Community Development Department approval
Applicant Signature
G Planningl2006PA06 0053 Roripangh SP Tract Maps Major ModPIanningIMap 29353 Rev Final COAs 5 06 doc
27
EXHIBIT B
FOR ATFACHMENT NO 5
CONDITIONS OF APPROVAL
PLANNING APPLICATION NO 010230
TENTATIVE TRACT MAP NO 29353
RResos 2002Resos 02113 5
EXHIBIT B
FOR ATTAHCMENT 5
CITY OF TEMECULA
CONDITIONS OF APPROVAL
Planning Application No PLANNING APPLICATION NO 010230 TENTATIVE
TRACT MAP NO 29353
Project Description The subdivision of 8047 acres into 39 lots and 8 street
lots which conform to the Planning Areas of the
Roripaugh Ranch Specific Plan
Assessors Parcel Nos 957130001 and 002 957340001 003 007 008 and
958260001 and 002
Approval Date November 26 2002
Expiration Date November 26 2004
PLANNING DIVISION
General Requirements
The tentative subdivision shall comply with the State of California Subdivision Map Act
and to all the requirements of the Temecula Subdivision Ordinance unless modified by
the conditions listed below A time extension may be approved in accordance with the
State Map Act and City Ordinance upon written request if made 30 days prior to the
expiration date
The permitteeapplicant shall indemnify protect and hold harmless the City and any
agency or instrumentality thereof andor any of its officers employees and agents from
any and all claims actions or proceedings against the City or any agency or
instrumentality thereof or any of its officers employees and agents to attack set aside
void annul or seek monetary damages resulting from an approval of the City or any
agency or instrumentality thereof advisory agency appeal board or legislative body
including actions approved by the voters of the City concerning the Planning Application
which action is brought within the appropriate statute of limitations period and Public
Resources Code Division 13 Chapter 4 Section 21000 et seq including but not by the
way of limitations Section 21152 and 21167 The City shall promptly notify the
permitteeapplicant of any claim action or proceeding brought forth within this time
period The City shall estimate the cost of the defense of the action and applicant shall
deposit said amount with the City City may require additional deposits to cover
anticipated costs City shall refund without interest any unused portions of the deposit
once the litigation is finally concluded Should the City fail to either promptly notify or
cooperate fully permitteeapplicant shall not thereafter be responsible to indemnify
defend protect or hold harmless the City any agency or instrumentality thereof or any
of its officers employees or agents Should the applicant fail to timely post the required
deposit the Director may terminate the land use approval without further notice to the
applicant
RResos 2002Resos 02113 6
This project and all subsequent projects within this site shall be consistent with Specific
Plan No 11 the Roripaugh Ranch Specific Plan
The project and all subsequent projects within this site shall comply with all mitigation
measures identified within the Final Environmental Impact Repod for the Roripaugh
Ranch Specific Plan and the approved Mitigation Monitoring Program thereof
Within thirty 30 days of the final approval of the project by the City Council the
tentative map shall be submitted to the Planning Department in final form for review and
approval It shall include all conditions of approval and all modifications made by the
Planning Commission and City Council Amended by the Planning Commission on
103002
The approval granted by this Resolution shall become effective upon the Effective Date
of the Development Agreement as the term Effective Date is defined in the
Development Agreement adopted concurrently with this Resolution
If Subdivision phasing is proposed a phasinq plan shall be submitted to and approved
by the Planning Director
The project and all subsequent projects within this site shall be subject to Roripaugh
Ranch Development Agreement PA990299
AC pavement shall be provided at intersections and approaches at all existing roads
Added by the Planning Commission on 103002
Prior to Issuance of Grading Permits
10 A copy of the grading plans shall be submitted and approved by the Planning Division
11 The applicant shall comply with the provisions of Chapter 824 of the Temecula
Municipal Code Habitat Conservation by paying the appropriate fee set forth in that
ordinance or by providing documented evidence that the fees have already been paid
12 Prior to the City approval of the grading plans or any other plans requiring MWD
clearance that may impact their property and easement the developer is responsible to
provide the City with MWDsclearance for the said plans
Prior to Recordation of the Final Map
13 The following shall be submitted to and approved by the Planning Division
a A copy of the Final Map
b A copy of the Environmental Constraint Sheet ECS with the following notes
i This property is located within thirty 30 miles of Mount Palomar
Observatory All proposed outdoor lighting systems shall comply with the
California Institute of Technology Palomar Observatory
recommendations Ordinance No 655
RResos 2002Resos 02113 7
ii The Roripaugh Ranch Environmental Impact Report EIR was prepared
for this project and is on file at the City of Temecula Community
Development Department Planning Division
iii Lots 31 32 and 33 shall be designated as permanent open space
A copy of the Covenants Conditions and Restrictions CCRs
i CCRsshall be reviewed and approved by the Planning Director The
CCRsshall include liability insurance and methods of maintaining open
space recreation areas parking areas private roads exterior of all
buildings and all landscaped and open areas including parkways
ii No lot or dwelling unit in the development shall be sold unless a
corporation association property owners group or similar entity has been
formed with the right to assess all properties individually owned or jointly
owned which have any rights or interest in the use of the common areas
and common facilities in the development such assessment power to be
sufficient to meet the expenses of such entity and with authority to
control and the duty to maintain all of said mutually available features of
the development Such entity shall operate under recorded CCRs
which shall include compulsory membership of all owners of lots andor
dwelling units and flexibility of assessments to meet changing costs of
maintenance repairs and services Recorded CCRs shall permit
enforcement by the City for provisions required as Conditions of Approval
The developer shall submit evidence of compliance with this requirement
to and receive approval of the city prior to making any such sale This
condition shall not apply to land dedicated to the City for public purposes
iii Every owner of a dwelling unit or lot shall own as an appurtenance to
such dwelling unit or lot either 1 an undivided interest in the common
areas and facilities or 2 a share in the corporation or voting
membership in an association owning the common areas and facilities
All future property owners shall agree to be a part of the proposed
Community Facilities District CFD or any other similar financing
mechanism
iV
14 Prior to the City approval of the grading plans improvement plans the final map or any
other plans requiring MWD clearance that may impact their property and easement the
developer is responsible to provide the City with MWDs clearance for the said plans
Prior to Issuance of Building Permits
15 With the exception of lot 22 fire station site no building permits shall be issued for the
lots created by this tentative map
PUBLIC WORKS DEPARTMENT
Unless otherwise noted all conditions shall be completed by the Developer at no cost to any
Government Agency
RResos 2002Resos 02113 8
General Conditions
16 It is understood that the Developer correctly shows on the Tentative Map all existing and
proposed easements traveled ways paseos pedestrian trails improvement constraints
detention basins and drainage courses and their omission will subject the project to
further review and may require revision
17 A Grading Permit for mass rough andor precise grading shall be obtained from the
Department of Public Works prior to commencement of any construction outside of the
Citymaintained road rightofway
18 An Encroachment Permit shall be obtained from the Department of Public Works prior to
commencement of any construction within an existing or proposed City rightofway An
Encroachment Permit may be issued for all roads designated as private streets
19 The Developer shall participate in a Cooperative Agreement with the County allowing the
City to act on their behalf if at the time prior to issuance of a grading permit in the
County area the annexation process has not been completed
20 The Developer shall submit a Maintenance Agreement to maintain flood control facilities
for the portions of Santa Gertrudis Creek and Long Valley Wash located within the
project site It must be mutually agreeable to the City Director of Public Works
Riverside County Flood Control Water Conservation District RCFCWCD and the
Home Owners Association HCA The Maintenance Agreement shall contain a funding
mechanism whereby all residential dwelling units in the proposed project will be equally
assessed for the Santa Gertrudis Creek and Long Valley Wash maintenance The
Maintenance Agreement shall be executed prior to issuance of the first building permit
21 The Developer shall agree to the formation of a Community Facilities District for the
construction of but not limited to road bridge drainage traffic signal intersection
landscape and fire station improvements in accordance with the Roripaugh Ranch
Specific Plan The form of the Agreement shall be subject to the approval of the City
Engineer and City Attorney and shall be executed prior to final map recordation
22 All easements andor rightofway dedications shall be offered for dedication to the
public or other appropriate agency and shall continue in force until the City accepts or
abandons such offers All dedications shall be free from all encumbrances as approved
by the Department of Public Works
23 The Developer shall obtain letters giving permission to grade or easements for any off
site work performed on adjoining properties The letters or easements shall be in a
format as directed by the Department of Public Works
24 The Developer shall make a good faith effort to acquire the required offsite property
interests and if he or she should fail to do so the Developer shall prior to submittal of
the Final Map for recordation enter into an agreement to complete the improvements
pursuant to the Subdivision Map Act Section 66462 and Section 664625 Such
agreement shall provide for payment by the Developer of all costs incurred by the City to
acquire the offsite property interests required in connection with the subdivision
Security of a portion of these costs shall be in the form of a cash deposit in the amount
RResos 2002Resos 02113 9
given in an appraisal report obtained by the Developer at the Developers cost The
appraiser shall have been approved by the City prior to commencement of the appraisal
25 A development phasing plan addressing the schedule of necessary infrastructure
requirements shall be approved by the Department of Public Works and the Planning
Director prior to approval of any subsequent application
26 The Developer shall pay to the City the Public Facilities Development Impact Fee as
required by and in accordance with Chapter 1506 of the Temecula Municipal Code and
all Resolutions implementing Chapter 1506
27 All utility systems such as electric including those which provide direct service to the
project site andor currently exist along public rightsofways adjacent to the site except
electrical lines rated 33 kv or greater gas telephone water sewer and cable TV shall
be placed underground with easements provided as required and designed and
constructed in accordance with City Codes and the utility provider
Circulation
28 Adequate primary and secondary access shall be provided for each phase of
development as approved by the Department of Public Works Vehicular access
easements shall be secured across undeveloped areas to provide secondary access
The exact location and number of access points shall be subject to review and approval
by the Department of Public Works at the time of submittal of future individual tentative
tract maps andor development applications Additional rightofway at entries may be
required to provide for turning lanes as directed by the Department of Public Works
29 Access along Murrieta Hot Springs Road Butterfield Stage Road Nicolas Road and the
Loop Roads as shown on this master tentative tract map shall be restricted except at
street intersections and driveways to be identified in individual tentative tract maps and
approved by the Department of Public Works
30 All street sections shall correspond with the Roripaugh Ranch Specific Plan Figures 24
24A 25 25A and 25A1 and by reference made a part of these conditions of
approval typical roadway cross sections and requirements of the Circulation Element of
the Citys General Plan and City ordinances and standards
31 The Developer shall obtain permission from adjacent affected property owners along
Nicolas Road and Butterfield Stage Road to allow for grading and any related driveway
improvements necessary to continue to allow legal vehicular access through the use of
some mechanism approved by the Citys Public Works Department including but not
limited to permission to grade offsite letters blanket or specific right of entry letters and
temporary construction easements
32 Prior to approval of the street improvement plans the developer shall demonstrate that
adequate sight distance at intersections and approved driveways meet City and Caltrans
standards to the satisfaction of the City Engineer
33 Bridge structure type shall be approved by the City Public Works Department and
Riverside County Flood Control and Water Conservation District Proposed bridges
shall provide acceptable crossing over waterways to accommodate al necessary
RResos 2002Resos 02113 10
vehicular pedestrian equestrian dry and wet utilities future utilities including but not
limited to conduit for fiber optic cable or traffic signal interconnect if not placed within
street pavement The bridge design shall include but not be limited to the following
studies foundation analysis scour analysis and protection measures
34 The Developer shall submit to the City Public Works Department for review and approval
street improvement plans signing and striping plans traffic signal plans and traffic
control plans for all improvements in the phasing section of these conditions
Traffic Mitigation Monitoring Program
35 The Traffic Mitigation Monitoring Program proposes that a traffic study be approved prior
to the issuance of the first building permit for each additional phase of development The
intent of the Traffic Mitiqation Monitorinq Proqram is not to redefine mitiqation
responsibility but rather to assist in the refinement of area improvement needs and the
timing of the improvements The traffic study would 1 document ambient traffic volumes
conditions 2 estimate trip generation for the particular development phase and 3
assess traffic conditions with the traffic added by the particular development phase The
exact study area to be addressed in each of the traffic studies should be defined through
discussions with the City Traffic Engineer In general the study area should include the
immediate access intersections and roadways which would serve the new development
phase and those critical offsite intersections and roadways that will provide primary
access to the new development Critical intersectionsroadways are defined as those
facilities that are experiencing high levels of peak period traffic congestion at the time
the traffic study is to be performed The traffic study findings would assist the City in
proactively planning for area roadway improvements
36 Ensuing Traffic Reports analyzing traffic impacts associated with subsequent
development stages of the Specific Plan shall be submitted to identify implementation
and timing of the necessary improvements to mitigate cumulative traffic impacts
Drainage
37 The Developer shall as required by the City and Riverside County Flood Control and
Water Conservation District protect downstream properties from damages caused by
alteration of the drainage patterns including concentration or diversion of flow and
increases in flow andor velocity Protection shall be provided by constructing adequate
channel improvements drainage facilities and by securing drainage easements as
necessary
38 Drainage and flood control facilities shall be provided in accordance with the
requirements of the City andor Riverside County Flood Control and Water Conservation
District RCFCWCD All drainage facilities shall be designed to convey 100year
storm flows subject to the approval of the Department of Public Works and
RCFCWCD as applicable
39 Prior to issuance of a grading permit affecting the creek areas the Developer shall
submit a Drainage Management Plan covering both Santa Gertrudis Creek and Long
Valley Wash to the City and RCFCWCD to review the adequacy of the proposed and
existing downstream drainage facilities The Drainage Management Plan will address
how the planned improvements will prevent downstream erosion and flooding impacts
RResos 2002Resos 02113 11
40
41
42
43
44
45
46
47
48
49
Prior to issuance of the first building permit the Developer shall provide a flood control
Maintenance Agreement for the portions of Santa Gertrudis Creek and Long Valley
Wash within the project site It must be mutually agreeable to the City Department of
Public Works the Riverside County Flood Control and Water Conservation District and
the homeowners association This agreement shall state that the City is only
responsible for maintaining flood control facilities under public roads and is not
responsible for maintaining the Santa Gertrudis Creek and Long Valley Wash channels
or detention basins
The Developer shall construct the proposed on and offsite drainage facility
improvements and interim detention basins andor flow by basins as recommended in
the Specific Plan and Drainage Study documents andor as directed by the Department
of Public Works and RCFCWCD as applicable
Prior to issuance of grading permits the Developer shall identify and design as
necessary interim channel improvements including but not limited to grading and
construction of detention basins before permanent channel improvements are
constructed
Drainage facilities within each phase shall be constructed immediately after the
completion of the site grading and prior to or concurrently with the initial site
development within that phase
The Developer shall accept and properly dispose of all offsite drainage flowing onto or
through the site The Developer in procuring the protection of downstream properties
has elected to construct two detention basins in the Plateau Area a detention basin in
Santa Gertrudis Creek and a flow by basin in Long Valley Wash These detention and
flowby basins shal be adequately sized so as not to increase the flow and velocities
exiting the project boundary
The Developer shall provide adequate bank protection as approved by the City
Department of Public Works and RCFCWCD to allow a bridge crossing at Nicolas
RoadCalle Girasol along Santa Gertrudis Creek Nicolas Road will not be accepted into
the Citys maintained street system until all offsite channel improvements are complete
and accepted by the City and RCFCWCD
The Developer shall provide maintenance roads to all proposed detention basins to
provide access for maintenance Road specifications such as width and type shall be
per Riverside County Flood Control and Water Conservation District requirements
Prior to issuance of grading permits the Developer shall coordinate any construction
that could impact Metropolitan Water District MWD facilities to assure that their
facilities are not damaged by project construction either onsite or offsite
The City reserves the right to require the developer to mitigate any concentrated offsite
flows and to adequately disperse them by the use of riprap or equivalent improvements
as approved by and to the satisfaction of the City Engineer This condition shall be in
force during the entire development process for the project
A Flood Plain Development Permit and Flood Study shall be submitted to the
Department of Public Works for review and approval The flood study shall be in a
RResos 2002Resos 02113 12
50
51
52
Water
53
54
55
56
57
format acceptable to the Department and include but not be limited to the following
criteria
a Drainage and flood protection facilities which will protect all structures by
diverting site runoff to streets or approved storm drain facilities
b Adequate provision shall be made for the acceptance and disposal of surface
drainage entering the property from adjacent areas
c Identify and mitigate impacts of grading to any adjacent floodway or floodplain
d The location of existing and post development 100year floodplain and floodway
Prior to issuance of a grading permit in the floodplain the Developer shall provide a
Conditional Letter of Map Revision CLOMR or equivalent Federal Emergency
Management Agency FEMA application and comply with that process
Prior to issuance of occupancy permits in those lots adjacent to either Santa Gertrudis
Creek or Long Valley Wash the Developer shall submit appropriate documentation to
the Federal Emergency Management Agency and obtain approval of Letter of Map
Revision LOMR
A flood mitigation charge shall be paid prior to issuance of grading permits The Area
Drainage Plan fee is payable to the Riverside County Flood Control and Water
Conservation District by either cashiers check or money order prior to issuance of
permits based on the prevailing area drainage plan fee If the full Area Drainage Plan
fee or mitigation charge has already been credited to this property no new charge needs
to be paid
and Sewer
Water and sewer facilities shall be installed in accordance with the requirements and
specifications of the City Eastern Municipal Water District EMWD and Rancho
California Water District RCWD Such requirements shall be applied at the subdivision
or plot plan stages of the development
Prior to the approval of subsequent development applications the Developer shall
comply with the Water Master Plan to EMWD and RCWD to check for adequacy of the
proposed water facilities The Developer shall obtain written approval for the water
system from EMWD and RCWD
Prior to the approval of subsequent development applications the Developer shall
comply with the Sewer Master Plan to EMWD to check for adequacy of the proposed
sewer facilities The Developer shail obtain written approval for the sewer system from
EMWD
Prior to approval of the final map the developer shall provide the City with adequate
documentation from the Iocat water purveyors EMWD and RCWD that they have
adequate water supplies to serve project startup through completion and full occupancy
according to the requirements of Senate Bills 221 and 610
The Developer shall install reclaimed water lines on the major road network to irrigate
landscaped areas to the satisfaction of the Public Works and Temecula Community
RResos2002Resos 02113 13
Services Departments if
fetu4tcfreclaimedwateris to be available to the site prior to the
construction of these roads or it is anticipated to be available in the near term
Amended by the City Council on 11262002
Grading
58 Prior to the issuance of any grading permit the Developer shall receive written clearance
from the following agencies State of California Department of Fish and Game US
Army Corps of Engineers and US Fish and Wildlife Service Where appropriate the
terms conditions and recommendations of the noted agencies shall be incorporated as
Conditions of Approval into the areas of development
59 No grading shall be permitted for any development area prior to tentative map approval
60 Grading plans and operations shall be in accordance with the California Building Code
City Grading Standards the recommendations contained in the Geotechnical Report or
any subsequent reports prepared for the project the conditions of the grading permit
and accepted grading construction practices and the recommendations and standards
specified in the Specific Plan and Environmental Impact Report EIR documents
61 Prior to issuance of any grading permit erosion control plans shall be prepared in
conformance with applicable City Standards and subject to approval by the Department
of Public Works The Developer shall post security and enter into an agreement
guaranteeing the grading and erosion control improvements
62 The Developer shall comply with the requirements of the National Pollutant Discharge
Elimination System NPDES permit regulated by the State Water Resources Control
Board and the Storm Water Pollution Prevention Plan SWPPP implemented by the
San Diego Regional Water Quality Control Board No grading shall be permitted until an
NPDES Notice of Intent NOI has been filed or the project is shown to be exempt
63 The Developer shall post a clearly visible sign at the intersection of Nicolas Road and
Calle Girasol to notify residents of the Nicolas Valley if and when blasting will occur at
least two days prior to scheduled blasting Any blasting activities will be limited to the
hours of 9 AM to 4 PM Monday through Friday Prior to blasting the Developer shall
obtain permission from the City Engineer to post notice in at least one newspaper of
local circulation at least one week in advance
64 Prior to issuance of grading permits the Developer shall submit a Dust Control Plan
DCP to SCAQrvID that is consistent with Rule 403 guidelines for approval The
Developer shall submit written proof to the City that SCAQMD has reviewed and
approved the DCP The DCP shall be applicable for all onsite as well as offsite work
and includes but is not limited to the following activities twice daily soil watering street
sweeping covering of trucks hauling soil away chip sealing access roads hydroseeding
exposed soil surfaces and adding chemical binders or surfactants to water used for
watering Aisc the Developer shall provide the City with documentation that appropriate
construction equipment that is anticipated to be used for more than 30 days has had
tuneups or equivalent work to assure Iow NOX emissions In addition all diesel
RResos 2002Resos 02113 14
65
66
67
68
69
70
71
72
73
equipment and vehicles must be equipped with particulate filters and use only Iow sulfur
fuels
Prior to issuance of grading and building permits the individual contractors shall submit
a Traffic Management Plan TMP to the Public Works Department that includes but is
not limited to scheduling receipt of construction materials to offpeak travel periods
routing construction traffic through areas of least impact sensitivity limiting lane closures
and detours to offpeak travel periods and staging areas away from existing residential
uses
Prior to issuance of a grading permit the Developer shall prepare and file a Noise
Control Plan NCP with the Public Works Department The NCP will be generally
consistent with the mitigation monitoring program and the Citys construction noise
ordinance
Graded but undeveloped land shall be maintained weedfree and planted with interim
landscaping such as hydroseed and temporary irrigation within ninety days of
completion of grading unless building permits are obtained
Paleontologists and Archeologists shall be present during grading including excavated
soil stockpiles in accordance with the Environmental Impact Report mitigation measure
An importexport route shall be submitted to the Department of Public Works prior to
issuance of any grading permit The plan shall include limitation to the duration of the
grading operation and construction activities a Traffic Control Plan and a daily time
schedule of operations
A Soils Report shall be prepared by a registered Civil or Soils Engineer and submitted to
the Department of Public Works with the initial grading plan check The report shall
address all soils conditions of the site and provide recommendations for the
construction of engineered structures and preliminary pavement sections
A Geotechnical Report shall be prepared by a registered engineer or engineering
geologist and submitted to the Department of public Works with the initial grading plan
check The report shall address special study zones and identify any geotechnical
hazards for the site including location of faults and potential for liquefaction and
landsides The report shall include recommendations to mitigate the impact of ground
shaking and liquefaction
If subsequent Geotechnical and Soils Reports determine that dewatering of the site is
necessary during construction necessary permits ie in compliance with NPDES permit
shall be obtained from appropriate agencies prior to approval of the grading plans
All public streets shall be maintained and cleaned if necessary on a daily basis during
grading operation and construction activities Cash deposit letter of credit or posting of
bond to guarantee maintenance of all public rightsofway affected by the grading
operations and construction activities shall be posted prior to issuance of grading
permits
RResos 2002Resos 02113 15
Specific Plan Phasing
74 Construction of the development permitted by the Specific Plan including recordation of
subdivision maps may be carried out in stages provided that adequate vehicular access
is constructed for all dwelling units in each stage of development and further provided
that such development conforms substantially with the intent and purpose of the Specific
Plan Conceptual Phasing Plan Figure 210 and Phasing of Road Improvements Section
226
75 In the event that the City is unable to construct the street and slopes acquire the
additional right of way and complete any related proceedings associated with that
process for the segment on Butterfield Stage Road from Chemin Clinet to Rancho
California Road by the 510th building permit the Developer shall be responsible for
completing this work by the 510th building permit
76 Prior to the issuance of the designated number of building permits for each phase the
developer or the CFD must construct the improvements identified below The City may
require additional or supplemental traffic studies prior to approval of future tentative tract
maps If these studies confirm that area intersections are operating below LOS D or
othenNise pose an unsafe condition then the developer shall be responsible for
mitigating these conditions in addition to the mitigation measures already identified in
the EIR
SPECIFIC PLAN PHASE 1
a ONSITE ROAD IMPROVEMENTS
Prior to issuance of the 34th building permit the following improvements shall be
completed
i Secondary Access Provide secondary access from Lots 1 34 67 to
Murrieta Hot Springs Road
Prior to issuance of the 108th building permit the following improvements shall be
completed
ii Improve Murrieta Hot Springs Road from existing improvements east of
Pourroy Road to the MWD Easement Specific Plan Arterial Highway
110 RAN to include dedication of fullwidth street rightofway installation
of fullwidth street improvements paving curb and gutter sidewalk street
lights drainage facilities signing and striping utilities including but not
limited to water and sewer and a 14foot wide raised landscaped median
All proposed improvements shall be coordinated with existing
improvements including raised landscaped median and lane width
transitions as approved by the City Traffic Engineer
iii Improve Murrieta Hot Springs Road from the MWD Easement to Butterfield
Stage Road Specific Plan Modified Arterial Highway 110 RW to
include dedication of fullwidth street rightofway installation of halfwidth
street improvements including a 14foot wide raised landscaped median
and a 14foot wide travel lane adjacent to the median on the unimproved
half paving curb and gutter sidewalk street lights drainage facilities
signing and striping and utilities including but not limited to water and
sewer Driveways shall be constructed to provide access to the MWD
property and easement
RResos 2002Resos 02113 16
iv Improve Butterfield Stage Road from Nicolas Road to Murrieta Hot Springs
Road Specific Plan Augmented Arterial Highway 122 RW to include
dedication of fullwidth street rightofway installation of halfwidth street
improvements plus a 14footwide raised landscaped median and a 12ofoot
travel lane adjacent to the median on the unimproved half paving curb
and gutter sidewalk street lights drainage facilities signing and striping
and utilities including but not limited to water and sewer
v Dedicate fullwidth rightofway on Butterfield Stage Road from Murrieta
Hot Springs Road to the northern project boundary Specific Plan Arterial
Highway 110 RNV
vi Improve Butterfield Stage Road from Nicolas Road to the southern project
boundary Specific Plan Arterial Highway 110 RN to include dedication
of fullwidth street rightofway installation of halfwidth street
improvements including a 14foot wide raised landscaped median and a
14foot wide travel lane adjacent to the median on the unimproved half
fullwidth bridge structures over Santa Gertrudis Creek and Long Valley
Wash paving curb and gutter sidewalk street lights drainage facilities
signing and striping and utilities including but not limited to water and
sewer
vii Improve Nicolas Road from Butterfleld Stage Road to the western project
boundary Specific Plan Modified Secondary Highway 110 RVV to
include dedication of fullwidth street rightofway installation of the
northerly halfwidth plus 10 feet of street improvements including paving
curb and gutter sidewalk soft surface path split rail fence street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
viii Improve South Loop Road from Butterfield Stage Road to the end of the
fire station site frontage Specific Plan Modified Principal Collector Road
76 RW to include dedication of fullwidth street rightofway installation
of the southerly halfwidth plus 6 feet of street improvements including
paving curb and gutter sidewalk street lights drainage facilities signing
and striping and utilities including but not limited to water and sewer
Prior to issuance of the 400 h building permit the following improvements shall be
completed
ix Improve F Street along Lot 8 frontage Specific Plan Modified Collector
Road 66 PJW to include dedication of fullwidth street rightofway
installation of fullwidth street improvements including paving curb and
gutter sidewalk street lights drainage facilities signing and striping and
utilities including but not limited to water and sewer
x Improve North Loop Road from Butterfield Stage Road to the east side of
Santa Gertrudis Creek Specific Plan Modified Principal Collector Road
76 RNV to include dedication of fullwidth street rightofway installation
of fullwidth street improvements including a fullwidth bridge over Santa
Gertrudis Creek paving curb and gutter sidewalk street lights drainage
facilities signing and striping and utilities including but not limited to
water and sewer
RResos 2002Resos 02113 17
OFFSITE ROAD IMPROVEMENTS
Prior to issuance of the 108th building permit the following improvements shall be
completed
i Improve Nicolas Road from the western project boundary to 450 feet east
of the existing Nicolas RoadCalle Girasol intersection Specific Plan
Modified Secondary Road 110 RW Section K to include installation of
40foot width on center improvements paving asphalt concrete berm
including signing and striping utilities including but not limited to water
and sewer and a 6foot wide curb separated asphalt concrete path on
the north side
ii The Developer shall obtain permission from adjacent affected property
owners to allow for grading and any related driveway improvements
necessary to continue to allow legal vehicular access onto Nicolas Road
through the use of some mechanism approved by the Citys Public Works
Depadment including but not limited to permission to grade offsite
letters blanket or specific right of entry letters and temporary
construction easements
iii Provide secondary access by constructing improvements for one of the
following options
a If Nicolas Road is designated as the secondary access route the
following improvements shall be completed
i Construct 40 foot on center improvements Specific Plan
Modified Secondary Road 110 RW Section K from 450
feet east of the existing Nicolas RoadCalle Girasol
intersection to Leifer Road including paving asphalt
concrete berm including signing and striping utilities
including but not limited to water and sewer and the full
width bridge structure over and within Santa Gertrudis
Creek
ii Realign existing Calle Girasol to its ultimate intersection
with Nicolas Road including rightofway acquisition
iii The Developer shall provide adequate bank protection as
approved by the City Department of Public Works and
RCFCWCD to allow a bridge crossing at Nicolas
RoadCalle Girasol along Santa Gertrudis Creek Nicolas
Road will not be accepted into the Citys maintained street
system until all offsite channel improvements are complete
and accepted by the City and RCFCWCD
b If Calle Chapos from Butterfield Stage Road to Walcott Lane and
Calle Chapos to Calle Girasol from Walcott Lane to the existing
Nicolas RoadCalle Girasol intersection is designated as
secondary access the following improvements shall be
completed
RResos 2002Resos 02113 18
i Construct 38foot width on center improvements Specific
Plan Modified Collector Road 66 RW Section L from
Butterfield Stage Road to the Nicolas RoadCalle Girasol
intersection including paving and signing and striping
ii Provide horizontal realignment and rightofway
acquisition as required by the City Fire Chief and City
Engineer from Walcott Lane to the existing Nicolas
RoadCalle Girasol intersection
c If Butterfield Stage Road Specific Plan Arterial Highway 110
RW is designated as secondary access construct halfwidth
improvements from the southern project boundary to Chimen
Clinet including dedication of fullwidth street rightofway
installation of halfwidth street improvements including a 14foot
wide raised landscaped median and a 14foot wide travel lane
adjacent to the median on the unimproved half paving curb and
gutter sidewalk street lights drainage facilities signing and
striping and utilities including but not limited to water and sewer
excluding any existing improvements
TRAFFIC SIGNALS WITHOUT A DEVELOPMENT AGREEMENT
The developer must make a fair share contribution towards the improvement of
the following intersections identified below The improvements listed below are
in addition to the existing improvements and lane configurations and shall
supplement but not replace existing turning movements Additional or
supplemental traffic studies shall be conducted prior to approval of future
tentative tract maps If these studies confirm that these intersections are
operating below LOS D or otherwise pose an unsafe condition then the
developer shall be responsible for mitigating these conditions in addition to the
mitigation measures already identified in the EIR
Prior to issuance of the 1st building permit in Lots 17 8 and 22
i 115 Freeway Southbound Ramps at Rancho California Road
southbound leftturn lane southbound free rightturn lane westbound free
rightturn lane and eastbound free rightturn tane
ii 1215 Freeway Southbound Ramps at Murrieta Hot Springs Road
southbound leftturn lane southbound rightturn lane eastbound through
lane eastbound rightturn lane westbound through lane and westbound
free rightturn lane
iii Ynez Road at Winchester Road southbound rightturn overlap
iv Ynez Road at Rancho California Road eastbound through lane
v North General Kearney Road at Nicolas Road traffic signal
vi Buttedield Stage Road at Rancho California Road traffic signal
vii Murrieta Hot Springs Road at Alta Murrieta lane improvements as yet
undetermined The developer shall provide the City of Temecula with a
letter from the City of Murrieta stating that a fair share contribution to
identified improvements at this intersection has been made
RResos 2002Resos 02113 19
viii Murrieta Hot Springs Road at Pourroy Road construct traffic signal and
related intersection improvements as warranted
TRAFFIC SIGNALS WITH A DEVELOPMENT AGREEMENT
The developer must bond and construct or make a fair share contribution
towards the improvement of the following intersections identified below The
improvements isted below are in addition to the existing improvements and lane
configurations and shall supplement but not replace existing turning movements
Additional or supplemental traffic studies shall be conducted prior to approval of
future tentative tract maps
Prior to issuance of the 1st building permit in Lots 17 8 and 22
i 1215 Freeway Southbound Ramps at rvlurrieta Hot Springs Road
southbound leftturn lane southbound rightturn lane eastbound through
lane eastbound rightturn lane westbound through lane and westbound
free rightturn lane
ii North General Kearney Road at Nicolas Road traffic signal
iii Buttedield Stage Road at Rancho California Road traffic signal
iv Murrieta Hot Springs Road at Alta Murrieta lane improvements as yet
undetermined The developer shall provide the City of Temecula with a
letter from the City of Murrieta stating that a fair share contribution to
identified improvements at this intersection has been made
v Murdeta Hot Springs Road at Pourroy Road construct traffic signal and
related intersection improvements as warranted
WATER IMPROVEMENTS
i Install water mains per Eastern Municipal Water District requirements
ii The Developer shall install reclaimed water lines to irrigate landscaped
areas to the satisfaction of the Public Works and Temecula Community
Services Departments if throughout the course of development and until
such time the project is complete reclaimed water lines become available
within 300 feet of any project boundary
SEWER IMPROVEMENTS
i Install sewer main in Murrieta Hot Springs Road west of Pourroy Road
ii Install sewer main in Nicolas Road per Eastern Municipal Water District
requirements
DRAINAGE IMPROVEMENTS
i Construct detention basin west of Lot 1 and detention basin south of Lot 5
along southern Plateau area
ii Construct storm drains and related outlet facilities as required by the
hydrologyhydraulics studies
SPECIFIC PLAN PHASE 2
Prior to issuance of the 510 building permit or any building permit in Phase 2 the
following improvements must be completed
RResos 2002Resos 02113 20
ONSITE ROAD IMPROVEMENTS
i Improve Murrieta Hot Springs Road from the MWD Easement to Butterfield
Stage Road Specific Plan Modified Arterial Highway 110 RVV to
include installation of remaining halfwidth street improvements paving
curb and gutter sidewalk street lights drainage facilities signing and
striping utilities including but not limited to water and sewer A 14foot
wide raised landscaped median shall be constructed in Phase 1
ii Improve Butterfield Stage Road from Murrieta Hot Springs Road to Nicolas
Road Specific Plan Augmented Arterial Highway 122 RVV to include
installation of remaining halfwidth street improvements paving curb and
gutter sidewalk street lights drainage facilities signing and striping and
utilities including but not limited to water and sewer A 14foot wide
raised landscaped median shall be constructed in Phase 1
iii Improve Butterield Stage Road from Nicolas Road to the southern project
boundary Specific Plan Arterial Highway 110 RNV to include
installation of remaining halfwidth improvements including installation of
paving curb and gutter sidewalk street lights drainage facilities signing
and striping utilities including but not limited to water and sewer A 14
foot wide raised landscaped median shall be constructed in Phase 1
iv Construct or bond for grading and fullwidth improvements on Butterfield
Stage Road from Murrieta Hot Springs Road to the northern project
boundary Specific Plan Arterial Highway 110 RNV to include
installation of fullwidth street improvements including a 14foot wide
raised landscaped median paving curb and gutter sidewalk street lights
drainage facilities signing and striping and utilities including but not
limited fo water and sewer
v Improve North Loop Road and South Loop Road Specific Plan Modified
Principal Collector Road 76 RAN to include dedication of fullwidth
street rightofway installation of fullwidth street improvements
construction of a fullwidth bridge over Long Valley Wash raised
landscaped median paving curb and gutter sidewalk street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
vi Improve Nicolas Road from Butterfield Stage Road to the western project
boundary Specific Plan Modified Secondary Highway 110 RW Section
D to include remaining southerly halfwidth street improvements including
paving curb and gutter sidewalk soft surface path split rail fence street
lights drainage facilities signing and striping and utilities including but
not limited to water and sewer
vii Improve F Street from the southern boundary of Lot 8 to Butterfield Stage
Road Specific Plan Modified Collector Road 66 RNV to include
dedication of fullwidth street rightofway installation of fullwidth street
improvements including paving curb and gutter sidewalk street lights
drainage facilities signing and striping and utilities including but not
limited to water and sewer
viii Improve E Street from F Street to Nicolas Road Specific Plan Modified
Collector Road 66 RNV to include dedication of fullwidthstreet rightof
RResos 2002Resos 02113 21
way installation of fullwidth street improvements including paving curb
and gutter sidewalk street lights drainage facilities signing and striping
and utilities including but not limited to water and sewer
OFFSITE ROAD IMPROVEMENTS
i Improve Butterfield Stage Road from the southern project boundary to
Rancho California Road excluding existing improvements Specific Plan
Arterial Highway 110 RNV to include installation of fullwidth
improvements except sidewalk on the County side paving curb and
gutter sidewalk street lights drainage facilities signing and striping
utilities including but not limited to water and sewer and a 14foot wide
raised landscaped median
ii Improve Nicolas Road from 450 feet east of the Nicolas RoadCalle
Girasol intersection to Leifer Road Specific Plan Modified Secondary
Road 110 RNV Section K to include dedication of fullwidth street
rightofway installation of 40footwidth improvements including fullwidth
bridge improvements at Santa Gertrudis Creek paving asphalt concrete
berm signing and striping utilities including but not limited to water and
sewer and a curb separated asphalt concrete path along the northerly
side
iii Improve Calle Chapos from Butterfield Stage Road to Walcott Lane
Specific Plan Modified Collector Road 66 PJVV Section L to include
installation of 38foot on center improvements to include paving asphalt
concrete berm signing and striping utilities including but not limited to
water and sewer
iv Realign existing Calle Girasol to its ultimate intersection with Nicolas
Road including rightofway acquisition
TRAFFIC SIGNALS WITHOUT A DEVELOPMENT AGREEMENT
The developer must make a fair share contribution towards the improvement of
the following intersections identified below Additional or supplemental traffic
studies shall be conducted prior to approval of future tentative tract maps If
these studies confirm that these intersections are operating below LOS D or
otherwise pose an unsafe condition then the developer shall be responsible for
mitigating these conditions in addition to the mitigation measures already
identified in the EIR
Prior to issuance of the 1st building permit in Phase 2 as defined in the Specific
Plan
i Butterfield Stage Road and Nicolas RoadNorth Loop Road construct
traffic signal and related intersection improvements as warranted
ii Butterfield Stage Road and Calle ChaposSouth Loop Road construct
traffic signal and related intersection improvements as warranted
iii Murrieta Hot Springs Road and Butterfield Stage Road construct traffic
signal and related intersection improvements as warranted
iv La Serena Way and Meadows Parkway construct traffic signal and
related intersection improvements as warranted
RResos 2002Resos 02113 22
v 115 Freeway Southbound Ramps at Winchester Road southbound left
turn lane southbound rightturn lane westbound through lane westbound
free rightturn lane eastbound through lane and eastbound free rightturn
lane
vi 115 Freeway Northbound Ramps at Winchester Road northbound left
turn lane northbound free rightturn lane westbound through lane and
westbound free rightturn lane
vii 115 Freeway Northbound Ramps at Rancho California Road
northbound leftturn and rightturn lanes
viii Ynez Road at Winchester Road southbound leftturn lane southbound
rightturn overlap and eastbound leftturn lane
ix Ynez Road at Rancho California Road westbound leftturn lane
westbound rightturn lane eastbound through lane southbound through
lane southbound free rightturn lane and eastbound free rightturn lane
x Margarita Road at Winchester Road eastbound leftturn lane southbound
rightturn lane westbound rightturn lane and southbound rightturn
overlap
xi Margarita Road at Rancho California Road northbound and southbound
through lanes southbound rightturn lane eastbound leftturn lane
eastbound rightturn overlap westbound leftturn lane northbound right
turn lane and westbound rightturn overlap
xii Margarita Road at Murrieta Hot Springs Road northbound shared left
through lane eastbound through lane and westbound through lane
xiii Winchester Road at Nicolas Road northbound leftturn lane northbound
free rightturn lane westbound leftturn lane northbound through lane
southbound leftturn lane southbound through lane and eastbound right
turn overlap
xiv Winchester Road at Murrieta Hot Springs Road northbound through lane
southbound through lane and westbound through lane
xv Butterfield Stage Road at Rancho California Road northbound leftturn
lane northbound through lane southbound leftturn lane southbound
through lane eastbound leftturn lane eastbound through lane westbound
leftturn lane and westbound through lane
vi Calle Contento at Rancho California Road eastbound leftturn lane
eastbound through lane westbound leftturn lane and westbound through
lane
TRAFFIC SIGNALS WITH A DEVELOPMENT AGREEMENT
The developer must bond and construct or make a fair share contribution
towards the improvement of the following intersections identified below The
improvements listed below are in addition to the existing improvements and lane
configurations and shall supplement but not replace existing turning movements
Additional or supplemental traffic studies shall be conducted prior to approval of
future tentative tract maps
RResos 2002Resos 02113 23
Prior to issuance of the 1st building permit in Phase 2 as defined in the Specific
Plan
i Butterfield Stage Road and Nicolas RoadNorth Loop
Road construct traffic signal and related intersection
improvements as warranted
ii Butterfield Stage Road and Calle ChaposSouth Loop
Road construct traffic signal and related intersection
improvements as warranted
iii Murrieta Hot Springs Road and Butterfield Stage Road
construct traffic signal and related intersection improvements
as warranted
iv Margarita Road at Murrieta Hot Springs Road
northbound shared leftthrough lane eastbound through lane
and westbound through lane
v Winchester Road at Nicolas Road northbound leftturn
lane northbound free rightturn lane westbound leftturn lane
northbound through lane southbound leftturn lane
southbound through lane and eastbound rightturn overlap
vi Winchester Road at Murrieta Hot Springs Road
northbound through lane southbound through lane and
westbound through lane
vii Butterfield Stage Road at Rancho California Road
northbound leftturn lane northbound through lane
southbound leftturn lane southbound through lane
eastbound leftturn lane eastbound through lane westbound
leftturn lane and westbound through lane
ONSITE DRAINAGE IMPROVEMENTS
i Install full width box culverts or equivalent drainage facilities where Santa
Gertrudis Creek crosses North Loop Road and Buttertieid Stage Road
The drainage facilities shall be designed to convey the tributary 100year
storm flows
ii Install full width box culverts or equivalent drainage facilities where Long
Valley Wash crosses South Loop Road and Buttertield Stage Road The
drainage facilities shall be designed to convey the tributary 100year
storm flows
iii Construct Santa Gertrudis Creek Channel through Lots 33 37 and 38
The channel shall be designed to convey the tributary 100year storm
flow and have adequate bank hardening andor other treatment to protect
the adjacent properties from flooding
iv Construct the detention basin on Lot 38 The detention basin should be
designed to regulate outflow rate such that the peak flow in Santa
Gertrudis Creek west of Butterfield Stage Road is equal to or less than
the undeveloped condition
v Construct the flowby basin on Lot 34 The flowby basin should be
designed to regulate outflow rate such that the peak flow in Long Valley
RResos 2002Resos 02113 24
Wash west of Butterfield Stage Road is equal to or less than the
undeveloped condition
vi Construct Long Valley Wash through Lots 34 and 35 The channel shall
be designed to convey the tributary 100year storm flow and have
adequate bank hardening andor other treatment to protect the adjacent
properties from flooding
OFFSITE DRAINAGE IMPROVEMENTS
i Construct Santa Gertrudis Creek Channel from the box culvert or
equivalent drainage facility crossing Butterfield Stage Road westerly to the
confluence with the existing Santa Gertrudis Creek The channel shall be
designed to convey the tributary 100year storm flow have adequate bank
hardening andor other treatment to protect the adjacent properties from
flooding The channel shall be extended a sufficient distance and designed
in a manner that flows will return to the existing conditions at the outlet
point Access roads shall be constructed as necessary to provide
adequate channel maintenance The channel access roads and
confluence structures shall be contained within drainage easements
obtained by the developer
WATER IMPROVEMENTS
i Install water mains per Eastern Municipal Water District requirements and
per Rancho California Water District requirements as necessary
ii The Developer shall install reclaimed water lines to irrigate landscaped
areas to the satisfaction of the Public Works and Temecula Community
Services Departments if throughout the course of development and until
such time the project road infrastructure is complete by phase reclaimed
water lines become available within 300 feet of any project boundary
SEWER IMPROVEMENTS
i Install a sewer main in Nicolas Road from Butterfield Stage Road to Leifer
Road and then to Joseph Road where it will connect to an existing 21inch
sewer line
ii Install sewer mains per Eastern Municipal Water District requirements
and City Standard No 609 Trench shall be per City Standard No 407
which wilt require the overlay of half of Nicolas Road between Leifer Road
and Joseph Road
COMMUNITY SERVICESDEPARTMENT
General Requirements
77 If any of the following conditions of approval differ from the Specific Plan text or exhibits
the conditions enumerated herein shall take precedent
78 All perimeter slopelandscape areas designated as Temecula Community Services
District TCSD maintenance areas shall be identified and offered for dedication to the
TCSD as a maintenance easement on the final map Underlying ownership of the
respective areas shall remain with the individual property owner or the Homeowners
Association All other landscape areas open space trails entry monumentation
RResos 2002Resos 02113 25
signage pedestrian portals bus shelters pedestrian bridge fences walls and private
gated areas shall be maintained by the Homeowners Association HCA private
maintenance association or property owner
79
80
81
82
83
84
85
86
87
The current park dedication requirement Quimby for this development is 2871 acres
based on 2015 singlefamily units This requirement shall be satisfied with the 197 acre
community sports park Lot 30 the 51 acre neighborhood park Lot 8 and the HCA
owned and maintained recreational areas identified in the Roripaugh Specific Plan
including the private recreation centers Lots 5 and 27 and the private mini park Lot 2
The design of the 197 acre community sports park Lot 30 and the 51 acre
neighborhood park Lot 8 shall be in substantial conformance with the conceptual
designs and guidelines identified within the Specific Plan Prior to submittal of
construction plans the developer shall meet with the Director of Community Services to
determine the location and specifications of the park amenities to be provided on site
Construction plans and specifications must be approved by the Director of Community
Services
All park and slopelandscape plans submitted for consideration for TCSD maintenance
shall be in conformance with the City of Temecula Landscape and Irrigation
Specifications and Installation Details and the Park Land and Landscape Dedication
Process
The design of the 197 acre community sports park Lot 30 and the 51 acre
neighborhood park Lot 8 shall provide for pedestrian circulation and shall be in
compliance with American with Disabilities Act ADA requirements
The developer is entitled to receive a credit against the park and recreation component
of the Citys Development Impact Fee DIF pursuant to a Development Agreement or a
DIF Credit Agreement between the applicant and the City prior to approval of the final
map
Construction of the 197 acre community sports park the 51 acre neighborhood park
landscaped medians and proposed TCSD slopelandscape maintenance areas shall
commence pursuant to a preconstruction meeting with the developer and TCSD
Maintenance Superintendent Failure to comply with the TCSD review and inspection
process may preclude acceptance of these areas into the TCSD maintenance programs
The Home Owners Association HCA portion of Lot 8 shall be developed concurrently
with the public park portion of Lot 8 The City will not accept the conveyance of the
public park until all improvements have been completed within Lot 8
The developer the developers successor or assignee shall be responsible for all
maintenance of the park sites slopeslandscape areas and landscaped medians until
such time as those responsibilities are accepted by the TCSD or other responsible party
The public parks shall be improved and conveyed to the City free and clear of any liens
assessment fees or easements that would preclude the City from utilizing the property
for public purposes A policy of title insurance for the value of the land and the cost of
RResos2002Resos 02113 26
the improvements and a soils assessment report shall also be provided with the
conveyance of the property
88 The design of the private minipark Lot 2 and the private recreation centers Lots 5 and
27 shall be consistent with the conceptual designs and guidelines identified in the
Roripaugh Specific Plan
89 Class II bicycle lanes as specified in the Roripaugh Specific Plan shall be identified on
the street improvements plans and constructed in concurrence with the completion of
said street improvements
90 A multiuse trail will be constructed along both sides of Long Valley Wash Lot 35 and
along the nodh side of Lot 34 If the maintenance roads for the Long Valley Channel are
proposed for this purpose written authorization from RCFCWCD must be provided to
the City allowing public access for trail purposes prior to approval of any tentative map
for the Valley portion If RCFCWCD determines that that the River Walk cannot be
located within the channel rightofway then the trail area shall be located outside the
flood control area These trails shall be designed and shown on the respective tentative
map for this area
91 The developer shall dedicate on the final map a fifteen 15 foot easement for public
access within the 30 foot fuel modification zone and construct an multiuse trail along the
westerly edge of Lot 22 the southerly edge of Lots 20 21 and 22 and the easterly edge
of Lots 19 and 34
92 All residential street lighting will be maintained by the Home Owners Association HCA
93 The developer shall contact the Citys franchise solid waste hauler for disposal of the
construction debris Only the Citys franchisee may haul construction debris
94 The developer shall provide adequate space for a recycling bin within any trash
enclosure in the commercial area Lot 10
Prior to Approval of the Final Map
95 All slopelandscape areas intended for dedication to the TCSD for maintenance shall be
identified on each final map by numbered lots with the square footage of said lot
numbers indexed as proposed TCSD maintenance areas
96 Construction drawings for all parks landscaped medians and proposed TCSD
slopelandscape maintenance areas shall be reviewed and approved by the Director of
Community Services prior to the approval of the respective final map
97 The developer shall post security and enter into an agreement to improve the public
parks landscaped medians and proposed TCSD slopelandscape maintenance areas
prior to the approval of the respective final map
98 An equestrian crossing shall be approved by the Water Quality Control Board WQCB
for the multipurpose trail connection between Lots 19 and 20 across the easterly edge
of Lot 34 prior to the approval of the respective final map
RResos2002Resos 02113 27
99 The developer shalt file a notice of intention with the Temecula Community Services
District to initiate election proceedings for acceptance perimeter slopelandscape into the
TCSD maintenance program All costs associated with this process shall be borne by
the developer
Prior to Issuance of Building Permits
100 Prior to issuance of building permits the developer shall provide TCSD verification of
arrangements made with the Citys franchise solid waste hauler for disposal of
construction debris
101 The private minipark Lot 2 shall be completed to the satisfaction of the Community
Services Director prior to the issuance of the 100 h residential building permit
102 The park portion of the private recreation center Lot 5 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 250th
residential building permit in Lots 13 4 6 and 7
103 The building and the pool portion of the private recreation center Lot 5 shall be
completed to the satisfaction of the Community Services Director prior to the issuance of
the 350th residential building permit Lots 13 4 6 and 7
104 The 51 acre neighborhood park Lot 8 shall be improved including the completion of
the 90day maintenance period and the conveyance accepted by the City Council prior
to the issuance of the 400th residential building permit for the overall Roripaugh
Development
105 The Paseo connecting Lot 7 and Lot 8 shall be completed to the satisfaction of the
Community Services Director prior to the issuance or the 400th residential building permit
in Lots 13 4 6 and 7
106 The Nature Walk and adjacent landscape areas Lot 36 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 400th
residential building permit in Lots 13 4 6 and 7
107 The 197acre sports park Lot 30 shall be improved including the completion of the 90
day maintenance period and the conveyance accepted by the City Council prior to the
issuance of the 700th residential building permit for the overall Roripaugh Development
108 The park portion of the private recreation center Lot 27 shall be completed to the
satisfaction of the Community Services Director prior to the issuance of the 800th
residential building permit for the overall Roripaugh Development
109 The building and the pool portion of the private recreation center Lot 27 shall be
completed to the satisfaction of the Community Services Director prior to the issuance of
the 1150th residential building permit for the overalt Roripaugh Development
RResos 2002Resos 02113 28
110 The River Walk and the landscaping adjacent to the maintenance roads on both sides
of Long Valley Wash Lot 35 and along the north side of Lot 34 shall be completed prior
to the issuance of the 700th overall residential building permit in the project
111 If the maintenance road along the north side of Long Valley Wash cannot be used for a
multiuse trail a separate trail with landscaping shall be completed to the satisfaction of
the Community Services Director prior to the issuance of the 50th building permit in Lot
26
112 If the maintenance road along the south side of Long Valley Wash cannot be used for a
multiuse trail a separate trail with landscaping shall be completed to the satisfaction of
the Community Services Director prior to the issuance of the 75th building permit in Lots
23 24 and 25
113 A pedestrian bridge will be constructed across Long Valley Wash Lot 35 connecting
Lots 24 and 26 to the satisfaction of the Public Works Director and the Community
Services Director prior to the issuance of the 75th building permit in Lots 23 24 and 25
114 The developer shall construct a 15 foot soft surface trail within the 30 foot fuel
modification zone to the satisfaction of the Community Services Director along the
westerly edge of Lot 22 the southerly edge of Lots 20 21 and 22 and the easterly edge
of Lots 19 and 34 prior to the issuance of the first building permit in Lots 19 20 and 21
115 Prior to the installation of arterial street lights or issuance of building permits whichever
occurs first the developer shall file an application submit approved Southern California
Edison street light plans and pay the appropriate fees to the TCSD for the dedication of
arterial street lights into the appropriate TCSD maintenance program
Prior to Issuance of Certificates of Occupancy
116 Prior to the issuance of the first certificate of occupancy within each phase map the
developer shall submit the most current list of Assessors Parcel Numbers assigned to
the final project
117 It shall be the developers responsibility to provide written disclosure of the existence of
TCSD and its service level rates and charges to all prospective purchasers
FIRE DEPARTMENT
118 Any previous existing conditions for this project will remain in full force and effect unless
superceded by more stringent requirements here
119 Final fire and life safety conditions will be addressed when building plans are reviewed
by the Fire Prevention Bureau These conditions will be based on occupancy use the
California Building Code CBC California Fire Code CFC and related codes which
are in force at the time of building plan submittal
120 The Fire Prevention Bureau is required to set a minimum fire flow for residential land
division per CFC Appendix IIIA Table AIIIA1 The developer shall provide for this
project a water system capable of delivering 1500 GPM at 20PS1 residual operating
pressure with a 2hour duration The required fire flow may be adjusted during the
RResos2002Resos 02113 29
121
122
123
124
125
126
127
approval process to reflect changes in design construction type or automatic fire
protection measures as approved by the Fire Prevention Bureau The Fire Flow as
given above has taken into account all information as provided CFC 9032 Appendix
HA
The Fire Prevention Bureau is required to set minimum fire hydrant distances per CFC
Appendix IIIB Table AIllB1Standard fire hydrants 6 x 4 x 2 12 outlets shall be
located on Fire Department access roads and adjacent public streets Hydrants shall be
spaced at 500 feet apart at each intersection and shall be located no more than 250 feet
from any point on the street or Fire Department access roads frontage to a hydrant
The required fire flow shall be available from any adjacent hydrants in the system The
upgrade of existing fire hydrants may be required CFC 9032 90342 and Appendix
The Fire Prevention Bureau is required to set a minimum fire flow for commercial land
division per CFC Appendix IllA Table AIIIA1The developer shall provide for this
project a water system capable of delivering 4000 GPM at 20PSI residual operating
pressure with a 4 hour duration The required fire flow may be adjusted during the
approval process to reflect changes in design construction type or automatic fire
protection measures as approved by the Fire Prevention Bureau The Fire Flow as
given above has taken into account all information as provided CFC 9032 Appendix
The Fire Prevention Bureau is required to set minimum fire hydrant distances per CFC
Appendix IllB Table AIllB1Super fire hydrants 6 x 4 x 22 12 outlets shall be
located on Fire Department access roads and adjacent public streets Hydrants shall be
spaced at 350 feet apart at each intersection and shall be located no more than 210 feet
from any point on the street or Fire Department access roads frontage to a hydrant
The required fire flow shall be available from any adjacent hydrants in the system The
upgrade of existing fire hydrants may be required CFC 9032 90342 and Appendix
HIB
Maximum culdesaclength shall not exceed 1320 feet Minimum turning radius on any
culdesac shall be thirtyseven 37 feet for residential and fortyfive 45 feet for
commercial CFC 902223 CFC 902224
Private entry driveways with divider medians must be a minimum of 16 feet wide on
each side unless the median is held back 30 feet from face of curb of perpendicular
road
If construction is phased each phase shall provide approved access and fire protection
prior to any building construction CFC 87042 and 90222 This will include all internal
roads connecting roads between phases and construction gates All required access
must be in and available prior to and during ALL construction Phasing is approved on a
separate map and is ultimately subject to final approval in the field
Prior to building construction all locations where structures are to be built shall have
approved temporary Fire Department vehicle access roads for use until permanent
roads are installed Temporary Fire Department access roads shall be an all weather
surface for 80000 lbs GVW CFC 87042 and 902222
RResos 2002Resos 02113 30
128 Prior to building final all locations where structures are to be built shall have approved
Fire Department vehicle access roads to within 150 feet to any portion of the facility or
any portion of an exterior wall of the buildings Fire Department access roads shall be
an all weather surface designed for 80000 lbs GVW with a minimum AC thickness of
25 feet CFC sec 902
129 Fire Department vehicle access roads shall have an unobstructed width of not less than
twentyfour 24 feet and an unobstructed vertical clearance of not less than thirteen 13
feet six 6 inches CFC 902221
130 Prior to building construction dead end roadways and streets in excess of one hundred
and fifty 150 feet which have not been completed shall have a turnaround capable of
accommodating fire apparatus CFC 902224
131 Prior to building construction this development and any street within serving more than
35 homes or any commercial developments shall have two 2 points of access via all
weather surface roads as approved by the Fire Prevention Bureau CFC 90221
132 Prior to issuance of building permits the developer shall furnish one copy of the water
system plans to the Fire Prevention Bureau for approval prior to installation Plans shall
be signed by a registered civil engineer contain a Fire Prevention Bureau approval
signature block and conform to hydrant type location spacing and minimum fire flow
standards After the plans are signed by the local water company the originals shall be
presented to the Fire Prevention Bureau for signatures The required water system
including fire hydrants shall be installed and accepted by the appropriate water agency
prior to any combustible building materials being placed on an individual lot CFC
87043 901222and National Fire Protection Association 24 141
133 Prior to issuance of a Certificate of Occupancy or building final Blue Reflective
Markers shall be installed to identify fire hydrant locations CFC 90143
134 All manual and electronic gates on required Fire Department access roads or gates
obstructing Fire Department building access shall be provided with the Knox Rapid entry
system for emergency access by firefighting personnel CFC 9024
Special Conditions
135 Prior to issuance of building permits fuel modification plans shall be submitted to the
Fire Prevention Bureau for review and approval for all open space areas adjacent to the
wildlandvegetation interface FC Appendix IIA
136 Prior to issuance of building permits plans for structural protection from vegetation fires
shall be submitted to the Fire Prevention Bureau for review and approval The measures
shall include but are not limited to enclosing eaves noncombustible barriers cement or
block walls and fuel modification zones CFC Appendix IIA
137 Prior to map recordation the applicant shall submit to the Fire Prevention Bureau a
georectified pursuant to Riverside County standards digital version of the map
including parcel and street centerline information The electronic file will be provided in a
ESRI ArclnfoArcView compatible format and projected in a State Plane NAD 83
California Zone VI coordinate system The Bureau must accept the data as to
RResos 2002Resos 02113 31
completeness accuracy and format prior to satisfaction of this condition
OTHER AGENCIES
138 Flood protection shall be provided in accordance with the Riverside County Flood
Control Districts transmittal dated October 21 2002 a copy of which is attached The
fee is made payable to the Riverside County Flood Control Water District by either a
cashiers check or money order prior to the issuance of a grading permit unless
deferred to a later date by the District based upon the prevailing area drainage plan
fee
By placing my signature below I confirm that I have read understand and accept all the above
Conditions of Approval I further understand that the property shall be maintained in
conformance with these conditions of approval and that any changes I may wish to make to the
project shall be subject to Community Development Department approval
Applicant Signature
RResos 2002Resos 02113 32
DAVID P ZAPPE
General ManagerChief Engineer
OCT 2 4
RIVERSIDE COUNTY FLOOD CONTROL
AND WATER CONSERVATION DISTRICT
1995 MARKET STREET
RIVERSIDE CA 92501
9099551200
9097889965 FAX
511801
City of Temecula
Planning Department
Post Office Box 9033
Temecula California 925899033
AttenUonM AAIA
Ladles and Gentlemen
The District does not normally recommend conditions for land divisions or other land use cases in incorporatedcitiesTheDistrictalsodoesnotplancheckcitlandusecasesorprovideStateDivisionofRealEstatelettersor
other flood hazard reports for sucncases Distnct commentsrecommendations for such cases are normally limited
to items of specific interest to the District including District Master Drainage Plan facilities other regional flood
control and drainaqe facilities which could be considered a logical componemor extension of a master plan system
and District Area urainage Plan fees development mitigation fees In addition information of a general nature is
provided
The District has not reviewed the proposedproject in detail and the folowing checked comments do not in any way
constitute or imply Distdct approval or en3orsementof the proposec project with respect to need hazard public
health and safety or any other such ssue
This prgject would not be impacted by Distdct Master Drainage Plan facilities nor are other facilities of
regional nterest proposed
This project involves District Master Plan facilities The Distdct will accept ownership of such facilities on
written request of the City Facilities must be constructed to District stanoards and District plan check and
inspection will be required for Disct acceptance Plan check inspection and administrabve fees will be
required
This project proposes channels storm drains 36 inches or larger in diameter or other facilities that could be
considered regional in nature andor a logical extension of the adopted 14za FMasterDrainagePlanTheDistdctwouldconsideracceptingownershipetsuchtaealitlesbnwnttenrequest
of the City Facilities must be constructed to District standards a nd Distdct pJan check and inspection will
be required for Distdct acceptance Plan check inspection and acm nistrative rees will be required
ThisprojectislocatedwithinthelimitsoftheDistrictsuorffVurAreaDrainagePlanforwhichdrainaefeeshavebeenadoptedapplicableteesshouldbepaidby cashierscheckormoneyorderonlytomeFloodControlDistrictpdorreiSsuanceofbuildingorgradingpermitswhichevercomesfirstFeestobepaidshouldbeattherateineffectatthetimeofissuanceoftheactualpermitGENERALINFORMATION Thisproject mayrequire aNationalPollutantDischargeEliminationSystemNPDESpermitfromtheStateWaterResourcesControlBoardClearanceforgradingrecordationorotherfinalapprovaishouldnotbegivenuntiltheCityhasdeterminedthattheprojecthasbeengrantedapermitorisshowntobeexemptIfthisprojectinvolvesaFederalEmergencyManagementAgencyFEMAmappedfloodplainthentheCityshouldrequire theapplicanttoprovideallstudiescalculationsplansandomerreformationrequiredtomeetFEMArequirementsandshouldfurtherrequirethat theapplicantobtainaConditionalLetterofMapRevisionCLOMRpriortogradingrecordationorotherfinalapprovmoftheprojectandaLetterofMapRevisionLOMRpriortooccupancyIfa naturalwatercourseormappedflood plainisimpactedbythisprojecttheCityshouldrequiretheapplicanttoobtainaSection16011603AgreementfromtheCaliforniaDepartmentofFishandGameandaCleanWaterACtSection404PermitfromtheUSArmyCorpsofEngineersorwrittencorrespondencefromtheseagenciesindicatingtheprojectisexemptfromthesereqmrementsACleanWaterAct Section 401WaterQualityCertmcationmay
berequiredfromthelocalCaliforniaRegionalWaterQualityControlBoardpdortoissuanceoftheCorps404permitSTUARTEMCKIBBINSeniorCivilEngineerDateO